Enwork Ambition Beams Installation Manual
Text of the manual
2) Tools and Supplies Required
INSTALLATION GUIDE
Drill/Driver
1/4” Hex Drive Bit or
Allen Wrench
#2 Square Drive Bit
#2 Phillips Drive Bit
3/8” Nut Driver Bit
Socket Wrench/Ratchet
Socket Wrench Extension
1/4” & 3/8” Socket Set
5/16” Drill Bit
1) Parts and Fasteners Included
INSTALLATION GUIDE
Aluminum Support Bar (1x)
5/16”-18 x 2 3/4” Socket
Head Screw (1x)
5/16” Square Nut (1x)
1/4”-20 x 1/2” Hex Bolt (16x)
10-24 x 3/8” Phillips Machine
Screw (2x)
10-24 Hex Nut (2x)
Jig for Support Bar Holes
Jig for Connection Block Holes
Connection Block (2x)
1) Parts and Fasteners Included
INSTALLATION GUIDE
1-1/4” Socket Head Screw
(6x)
1/4” Split Lock Washer (6x)
#8-32 x .75, Flat Head
Machine Screw
Connection Block Plate (2x)
3) Assembly Overview
INSTALLATION GUIDE
Step 1
Step 2
Step 3
1. Decide which end of the existing
beam is receiving the add-on and
remove the leg bolts to move the end
leg temporarily, so that the beam is still
supported.
2. Remove top cap, end cap, and
beltways of existing beam, and keep for
later.
3a.) Using the support bar jig provided,
slide it onto the top of the beam as
shown in red for clarity. Mark hole
locations (8x) with a hammer punch or
marker. Drill thru 1 wall using the 5/16”
drill bit. Remove jig when complete.
Note: If power blocks are interfering with
this step, please see next sheet for power
block removal. Otherwise, proceed to
step 4.
3) Assembly Overview
INSTALLATION GUIDE
Power Block Removal
3b.)
1) Disconnect jumper(s).
2) Remove power block from brackets.
3) Remove the brackets from the beam by removing 4 screws.
Jumper
Power block
Brackets
3) Assembly Overview
INSTALLATION GUIDE
Step 4
Step 5
Step 6
4. Using the connection block jig
provided, slide it onto the bottom of
the beam as shown in red for clarity.
Mark hole locations with a hammer
punch or marker. Mark as many holes
as available. Drill thru 1 wall using the
5/16” drill bit. Remove jig when
complete.
5. Attach a new mid cap from the
received add-on beam kit using #8-32 x
.75” flat head screw (4x).
6. Using the newly drilled holes from
step 4, attach the connection block &
plate as shown on the underside of the
beam with 1-1/4” socket head screw and
1/4” lock washer (2x).
3) Assembly Overview
INSTALLATION GUIDE
Step 7
Step 8
Step 9
7. Slide the support bar into the
opening. Line up the newly drilled holes
from step 3. Finger tighten the 1/2” hex
bolts in (8x).
8. With a mid-run end cap on the new
received beam, slide it onto the support
bar lining up the holes. Finger tighten
1/2” hex bolts (8x). Fasten the tops of
the end caps with the 3/8” machine
screw and hex nut provided (2x). Note:
Beam may need to be temporarily
supported during this step.
9. Insert the 2 ¾” socket head bolt into
the large round hole on one connecting
block and insert the square nut into the
rectangular hole on the other
connecting block (shown in red for
clarity). Note: With socket wrench, fully
tighten while beam is level and
connection is flush.
3) Assembly Overview
INSTALLATION GUIDE
Step 10
Step 12
Step 13
10. Finish tightening the 1/2” hex bolts
with a ratchet into the support bar (16x)
from step 7 and 8. Check that the beam
remained level.
11. Re-attach power block(s), power/data
cords & jumpers to desired locations.
12. Re-attach top cap, end cap, and
beltways from step 1.
13. Relocate existing leg from step 1 to
the new end position and fasten with the
leg bolts saved from earlier. Depending
on your application, an additional mid-
leg may be required – refer to your
Enwork quotation or Enwork Price List
for Ambition Planning – Configuration.
12900 Christopher Drive Lowell, MI 49331
800.815.7251 www.enwork.com
Specifications subject to change without notice.