Installation and Operation Instructions

Solar System with KPS1 Collectors

General Installation and Operation Instructions .…....……...…….…................................. 3

1 Supply of Mounting System ..……........……...……..………....……..……............................ 4 2 Sloping Roof Mount ..........................................………………………................................. 5 2.1 Preparation ...………………………………………....………............................................ 6 2.1.1 Roof anchor installation for sloping roofs ..……………………................................ 6 2.1.2 Installation with roof anchors and rafters ………………………............................... 6 2.1.3 Installation with roof anchors for slate, shingle or metal roofs ............................... 7 2.1.4 Installation with bolts for fixing rails onto a roof .................................................... 7 2.1.5 Installation with universal templates for Cembrit roofs ...................................... 9 2.2 Installing rails onto roof anchors ….........……………………………............................... 9 2.3 Collector mounting …………………………….………………………............................... 9 3 Connection Pipe Passage through a Roof …...…...…................................................... 10 4 Flat Roof Mount …………....……….…………………........................................................ 11 4.1 Overview ………..........…….……………….………………………................................. 11 4.2 Flat roof support mounting ………………….....………….............................................. 12 5 Hydraulic Connection …………………………………………………................................. 15 5.1 Collector connecting .......………………………………………………............................ 15 5.2 Collector interconnecting …………………..…………………………............................. 15 6 Temperature Probe Positioning …………………………………….................................... 16 7 Pump Station ………………………………………..........…………...................................... 17 8 Expansion Vessel Sizing and Working Pressure Calculation ………........................... 18 8.1 Expansion vessel sizing ……………………………...…………..................................… 18 8.2 Calculation of a system working pressure ……………..………................................… 18 8.3 Calculation of an expansion vessel preset pressure …………................................…. 18 8.4 Examples of calculating working pressure and expansion vessel pressure ...........…. 18 8.4.1 Example of calculating system working pressure ………......................…………. 18 8.4.2 Example of calculating expansion vessel pressure …………...................………. 18 9 Installation of Air Release Valves …………………..………….….................................…. 19 10 System Filling, Flushing, Leak Test and Air Bleeding …............................................. 20 10.1 Filling ……………………………………......………………………....................………. 20 10.2 Flushing …………………………………………........………………..................………. 20 10.3 Air bleeding …………………………….................……………….....................………. 20 10.4 Leak test ………………….............................….……………………....................……. 20 11 Commissioning …………..……...............................................................................……. 21 12 Operation, Checks and Maintenance ………........…………………...........................…. 21 13 Servicing and Warranty …………..................………………………….........................…. 21 14 Technical Data .…...…...................................................…...….....................…............… 22 15 Connection dimensions…………………..……...........................................................…. 24 16 Annual Check Description ............................................................................................. 25 17 Service sheet ..................................................................................................................... 26

REGULUS KPS1 Flat Solar Collectors are designed for

solar domestic hot water heating (DHW), support- and pool heating with solar energy. Solar radiation pene­ trates the glass and is intercepted by an efficient absorp­ tion layer applied on an aluminium absorber. The heat is then transferred into heat transfer fluid. The absorber is sealed in a compact frame with high quality thermal insulation. The collectors are designed for year round operation, that’s why they work in a separate primary circuit filled with antifreeze heat carrier. The collectors are not intended for direct water heating. If different heat transfer fluid is used than specified by the manufacturer, irreversible damage to the collector may be done. Transport, handling and storing Collectors shall be transported in their original packing, in upright position (standing on their shorter side) or lying horizontal with glass upwards, stack of max. 10 pieces on a pallet. During handling the collector glass shall be always fac­ ing upwards. Please check the condition of the collector upon re­ ception from your supplier or forwarder. Later claimed mechanical damage (frame, glass, connection) will be refused. When stored, the collector shall not be exposed to rain and its absorber exposed to solar radiation. Scope of supply 1. KPS1 Collector 2. Instruction manual 3. Warranty Certificate 4. Commissioning form - info for the Manufacturer General instructions for installation The installation and commissioning must be done by a trained worker or a specialized company. During installation and before commissioning, it is nec­ essary to cover collectors in order to avoid overheating and possible burn injury to the installer. Prior to installation, conditions set by the roofing man­ ufacturer and the max. permissible roof load shall be checked. Mounting method for solar collectors shall always respect local conditions, i.e. roof inclination and weath­ er influence on the overall load on the collector. Kindly consult the fixing method with a structural statics expert. During installation the collectors and accessories shall be handled carefully. Defects caused by improper han­ dling or DIY installation are not cover by warranty. Generally valid rules and standards for occupational safety shall be respected during installation. This con­ cerns mainly technicians walking on a roof and the se­ curing the area against objects falling down from a roof. Only REGULUS fixing elements may be used. Other fixing elements may be used only with a written approval by REGULUS company. Collectors shall not be exposed to solar radiation until commissioned. The absorption surface may get dam­ aged. Collectors shall be installed and operated in compliance with this Manual and with respective generally valid rules and norms. Collector placing The collector must be placed outdoors. The glass absorption surface should be orientated to South, with deviations not over 45° (Southwest or Southeast). For a year round operation the right inclination angle is 40°- 50°, for summer operation smaller inclination is better (30°). The collector may be placed also vertically (90° inclination, e.g. on an outer wall) which is ideal for winter operation. Collectors shall be installed with the sheath upwards as marked. A collector inclination shall not be less than 20°. On inclined roofs it is recommended to install solar collectors as close to the roof ridge as possible. Should this solution be impossible, then protec­ tions against snow slide shall be installed above the collectors. The numbers of roof anchors shown in the Mounting Kits for Fixing and Connecting Regulus Solar Collectors are designed for the following load: Max. permissible snow and wind load ≤ 1,8 kN/m2 Max. permissible wind load - negative pressure ≤ 1,0 kN/m2 The customer/user shall be informed about this fact prior to starting installation of a solar system. If a higher load than shown above is expected in the area in question, a statics expert shall be consulted and more roof anchors designed, or other measures taken that would ensure safe collector fixing. Regulus refuses any responsibility for damage caused by wrong design of collector fixing. Lightning protection Lightning protection is obligatory for solar systems. When installed on a roof, collectors must be wired to lightning protection equipment. Czech norm ČSN EN 62 305 shall be observed.For other countries check with local authorities. GENERAL INSTALLATION AND OPERATION INSTRUCTIONS

Mounting kits for fixing and connecting KPS1 solar collectors

Code Connection kit for a KPS1 (G3/4“ M inlet and outlet, 2 plugs, G3/8“F for air vent valve, sheath for solar temperature sensor) 7710 Fixing kit for one KPS1 collector *[for 4 anchors or 2 supports+1 strut]] 12178 Fixing and interconnection kit for 2 KPS1 collectors *[for 6 anchors or 3 supports+1 strut] 12179 Fixing and interconnection kit for 3 KPS1 collectors *[for 8 anchors or 4 supports+1 strut] 12180 Fixing and interconnection kit for 4 KPS1 collectors *[for 10 anchors or 5 supports+1 strut] 12181 Fixing and interconnection kit for 5 KPS1 collectors *[for 10 anchors or 5 supports+1 strut] 12182 * Roof fixing and interconnection kits are necessary to create a hydraulically connected collector array fixed to 2 mounting rails. The kits contain interconnecting fittings with insulation, two mounting rails, fastening material for mounting collectors onto the rails. They do not involve any roof anchors, supports, struts. These shall be select­ ed from the following chart by the roof type and roofing material. Supports and strut for flat and sloping roof installation Code Triangle support 15° 11979 Triangle support 25° 10975 Triangle support 45° 6859 Strut incl. screws for triangle supports for flat roofs 9563 Supports for sloping roof installation Code Triangle support 15° 10748 Triangle support 25° 8805 Triangle support 45° 10094 Triangle support 60° 9631 Anchors for various roofing types Code Stainless steel anchor for slate roofs 11574 Anchor for pantiles - hot-dip galvanized steel 7929 Stainless-steel anchor for pantiles 6857 Stainless steel anchor for pantiles - rafter mounted, incl. self tapping screws 10159 Bolt for fixing rails onto a roof 7320 1. DELIVERY OF MOUNTING SYSTEM

Flat plate collector

16277 2 Roof anchor with M8 bolt with special head for rails 6857 or other, depending on roofing type Triangle supports for inclination adjustment, suitable for anchors for sloping roofs - 15°, 25°, 45° and 60° angle 11748, 8805, 10094, 9631 Interconnecting pipes Fixing and interconnection kits No. of collectors (kit code) Item code 1 2 3 4 5 (12178) (12179) (12180) (12181) (12182) 3 Aluminum rail, 2 pieces 1.12 m 2.21 m 3.32 m 4.42 m 5.52 m 6949 4 M8 nut for the rails 4 pcs 8 pcs 12 pcs 16 pcs 20 pcs 6925 5 M8×20 bolt with allen head 4 pcs 8 pcs 12 pcs 16 pcs 20 pcs 12136 6 Retaining side bracket for KPS 4 pcs 8 pcs 12 pcs 16 pcs 20 pcs 12141 7 Retaining bracket for collector bottom 2 pcs 4 pcs 6 pcs 8 pcs 10 pcs 11690 8 Compression nut and ring for collector inter­ connection - 2 pcs 4 pcs 6 pcs 8 pcs 7629 9 Insulation 35 mm diam., 19 mm thick 0.5 m 0.75 m 1 m 1.5 m 2 m 7188 10 Base rail emd plug 4 pcs 4 pcs 4 pcs 4 pcs 4 pcs 11773 Insulation tape 0.8 m 1 m 1.5 m 2 m 2.5 m 7227 1 8 3 2 6 7 5 4 9 10 2. SLOPING ROOF MOUNT Fig. 1 Collector installation on a sloping roof Expansion mount and interconnection kits for 1 KPS1+ANT solar collector Code Expansion mount and interconnection kit for 1 KPS1+ and KPC1+ solar collector 12183

2.1 Prior to installation

Prior to installation of solar collectors, select a suitable position respecting the following conditions: • roof facing South • roof inclination (25°- 45°) • unshaded place • accessible for servicing • permissible roof load • shortest possible distance between the collectors and (accumulation) tank Further have ready the necessary material, tools and safety equipment for working on a roof. Check if the roofing manufacturer offers roof hooks and if the roof warranty will not be violated. 2.1.1 Installation with roof anchors and au­ xiliary boards Prior to installing anchors on auxiliary boards, the fo­ llowing shall be ensured: • The auxiliary board length shall exceed the length of the rail by at least 200 mm on each end. • The auxiliary board width shall be between 100 and 200 mm. • It shall be 30 mm thick • The height of the auxiliary board from the counter batten shall be equal to the batten thickness which can be reached by underlying the auxiliary board (see Fig. 3). Installation • Remove roofing so that auxiliary boards can be inserted (approx. distance between boards 1600-1800 mm). For roof tiles, just shifting them upwards in the length of the auxiliary board is sufficient (see Fig. 4). • Fix the auxiliary boards to battens so that the distribu­ tion of anchors resembles the positions in Fig. 2. At the same time screw the boards so high that the roof anchor does not hinder placing the roof tile with the right overlap (see Fig. 8). • Hang the roof anchors onto the auxiliary board respecting their distribution shown in Fig. 2. • Fix the anchors using stainless steel screws. 2.1.2 Installation with roof anchors for rafters For tiled roofs, rafter anchors can be used. Either a fixed (not adjustable) stainless-steel hook (Fig.7a) can be used, or an adjustable aluminum anchor (Fig. 7b) that enables horizontal shift of the anchor along the fixing 40 30 10 30 30 auxiliary board battens counter batten rafter waterproofing membrane underlay No. of collectors Total length No. of anchors 2 211 cm 6 3 319 cm 8 4 428 cm 10 5 536 cm 10 70.5 ~35 ~35 ~35 ~35 ~35 ~35 ~65 ~65 83 83 89.5 89.5 89.5 93 93 93 60 60 60 60 70.5 83 89.5 93 room for an auxiliary board counter batten rafter roof battens Fig. 3: Underlay to match thick battens Fig. 4: Remove roof tiles to fix the board Fig. 2: Layout of roof anchors auxiliary board width is 100 - 200 mm

board. For this anchor type also the rail fixing height can

be adjusted. Installation • Remove roofing in places where anchors shall be fixed (Fig. 6). The distance between anchors is defined in Fig. 2. • Cut the counter batten used for fixing the waterproo­ fing membrane. • Prior to the installation itself, use an underlay for anchors according to the thickness of battens and counter battens so that the anchors installed do not hinder proper positioning of the roof tiles. • Fix all the other roof anchors in the same way. • When installing roof anchors, maintain a direction parallel to the roofing (horizontal). 2.1.3 Installation with roof anchors for shin­ gle or metal roofs • Depending on the number of collectors, measure and calculate the positions for fixing roof anchors (Fig. 2). Such places shall be selected for mounting where anchors can be fixed sufficiently into the roof frame (rafter or similar). • Prior to fixing the anchor, apply suitable silicone putty on the contact surface (adjacent to the roofing) in order to prevent water leaking, or possibly use a sealing method recommended by the roofing manu­ facturer. • Simply lay the anchor onto the roof tiles and fix it with stainless-steel bolts. If the roofing is made of e.g. copper or zinc‑pla­ ted iron, then the anchor contact surface shall be isolated using suitable underlay (rubber). Other­ wise there is a risk of contact corrosion. 2.1.4 Installation using bolts for fixing rails onto a roof This method of installation is preferably used for roofs of bitumen corrugated sheets like Gutta or Onduline etc., or for corrugated eternit or metal sheets. Installation: • Depending on the number of collectors, locate the places for drilling holes and installing bolts into the roofing (Fig. 7d). Pre-drill 6 mm holes into a rafter or another massive wooden roof element for the bolts. Holes should be always drilled in the crest of the roofing wave, not in its valley, to avoid leakage. • The bolt shall be screwed into a rafter or another massive wooden roof element using spanner No. 7. • After screwing the bolt in, put on the rubber seal (Fig. 7d) and using a washer and nut, seal the drilled hole. counter batten rafter roof battens waterproofing membrane a • Then mount the U-shaped bracket (Fig. 9) on the bolt, between two nuts with a washer. • Then M8 bolt with floating head (for rails) shall be mounted into the other end of the bracket. First insert the floating head into the groove of the rail, and then tighten the bolt together with the rail to the U-shaped bracket using a nut and a serrated washer. Fig. 5: Fixing an auxiliary board and roof anchors Fig. 6: Opening the space for anchor fixing

Fig. 7: Basic overview of fixing elements

150 80 125 ≈160 35 Ø 10 40 45 150 7 5 RIGHT 10 - 30 mm Fig. 8: Right anchor position with roof tiles c) Stainless steel roof anchor for metal or slate roofing steel for pantiles a) Stainless steel anchor on rafter, for pantiles, incl. screws b) Roof anchor of stainless steel or zinc-plated steel for pantiles 70 ø 9 80 130 40 40 9 d) Roofing bolt for rail fixing RIGHT !

2.2 Fixing rails on roof anchors

• have ready two rails in the length required for the number and type of collectors to be installed. • Align the travelling screw head (Fig. 9) with the hori­ zontal rail and shift the rail onto it, or shift the screws into the rail first and fix to the anchors. Use serrated lock washers to fix the nuts. • Align the rails so that they lie in parallel to roof tiles. The diagonal between the rails must be of the same length: D1 = D2 (Fig. 10). • Then tighten the nuts on fixing bolts. 2.3 Collector mounting Collectors shall be covered during mounting. Installation: • Insert safety retaining brackets (Fig. 11) into the bottom rail, 2 brackets per collector. • Insert the retaining brackets into the bottom rail about 100 mm from the collector edge. • Lay the first collector carefully on the rails and align it in the brackets. Collectors shall be placed on the rails with marking upwards. The distance between the bottom edge of the collector and of the base rail depends on the design and size of the retaining brackets. The collector bottom edge is by circa 75 mm lower. • The distance between the collector edge and the end of the bottom rail is B = 35 mm (Fig. 12) roof anchor top / bottom rail M8 bolt with travelling head parallel D1 D2 Fig. 9: Fixing the rail onto the roof anchors Fig. 10: Alignment of base rails • Insert nuts into both the rails (Fig. 13). Put the retai­ ning side brackets on the rails and fix the collector using M8x20 bolts. • Lay the following collector next to the first one, main­ taining a sufficient gap. Then put on the threaded fittings (Fig. 15, pos. 9) and push the collector to the already mounted one until stop. Hold the fitting with a spanner to prevent turning and tighten the nuts. More on this in chapter 5 Hydraulic Connection. • Continue mounting further collectors in the same way (see page 15). Fig. 11: Inserting safety retaining brackets Safety retaining bracket Rails ~100 mm B 14 ~100 mm ~800 mm Fig. 12: Distance between the safety retaining brackets

For passing the connection pipes through a roof

e.g. ventilation tiles can be used, where the hole is modified according to the diameter of the pipe with insulation. Anyway standards of the roofing manufacturer shall be respected for pipe passage through a roof. 3. CONNECTION PIPE PASSAGE THROUGH A ROOF 5 – M8 nut for rail 6 – M8x20 allen head bolt 7 – Retaining bracket Fig. 13: Fixing the retaining brackets Fig. 14: Pipe passing through ventilation tile

4.1 - Overview

Pos. Item Code 1 Flat plate collector 16277 2 Triangular support Number of collectors (number of supports needed) 6859, 10975, 11979 1 (2) 2 (3) 3 (4) 4 (5) 5 (5) 3 Strut incl. bolts for triangular support 9563 Interconnection pipes Fixing and interconnecting kits Number of collectors (kit code) Item code 1 (12178) 2 (12179) 3 (12180) 4 (12181) 5 (12182) 4 Aluminum base rail, 2 pieces 1.12 m 2.21 m 3.32 m 4.42 m 5.52 m 6949 5 M8 nut for the base rail 4 pcs 8 pcs 12 pcs 16 pcs 20 pcs 6925 6 M8x20 bolt (allen head) 4 pcs 8 pcs 12 pcs 16 pcs 20 pcs 12136 7 Retaining side bracket 4 pcs 8 pcs 12 pcs 16 pcs 20 pcs 12141 8 Retaining bracket for collector bottom 2 pcs 4 pcs 6 pcs 8 pcs 10 pcs 11690 9 Compression nut and ring for collector interconnection - 2 pcs 4 pcs 6 pcs 8 pcs 7629 10 Insulation 35 mm diam., 19 mm thick 0.5 m 0.75 m 1 m 1.5 m 2 m 7188 11 Base rail end plug 4 pcs 4 pcs 4 pcs 4 pcs 4 pcs 11773 Insulation tape 0.8 m 1 m 1.5 m 2 m 2.5 m 7227 3 2 1 8 9 6 7 5 4 10 11 4. FLAT ROOF MOUNT Fig. 15 Collector installation on a flat roof Expansion mount and interconnection kits for 1 solar collector Code Expansion mount and interconnection kit for 1 KPS1 12183

4.2 - Flat roof support mounting

A flat roof support consist of two base rails, triangular supports and one strut. The number of triangular supports depends on the num­ ber of collectors. One strut is sufficient for supports for up to 5 collectors. Installation: • Lay two rails in parallel on the mounting surface, their pitch shall be 1660 mm. • The diagonals between the rails shall be of the same length: D1 = D2 (Fig. 16) • Insert the M8 bolt with a special head (Fig. 18) into the rail grooves. cca 350 mm D2 2 4 4 1660 mm T strut base rails L strut D1 Fig. 16: Aligning the rails and mounting the first triangular support • Assemble the triangular supports that come partially screwed together (Fig. 17). Fix the loose support ends with a bolt (Fig. 17) and tighten all connections. • Locate the positions to fix triangular supports. The distance of the first triangular support from the end of the rail shall be about 350 mm.. • Fix the L-support of the triangle to the base rail using screws, serrated lock washers and nuts for rails (Fig. 18) and tighten the connections. • Install the next triangular support in the same way. Its distance is the same as that of the roof anchors in Fig. 2.

• Install the strut between the two triangular supports

(Fig. 19). Following Fig. 19, insert special M8 nuts into the triangle support rail. Then lay the strut onto the rails and fix it with M8x12 bolts with washers (Fig. 19). • Continue assembling the remaining triangular supp­ orts with a pitch as shown in Fig. 2. Adjust this distan­ ce so that the pitch of the triangular supports is similar to that of roof anchors in Fig. 2. After fixing the strut and other supports, kip the entire structure into the position intended for collector installation. (The strut is upright, T rail of each triangular support lies on the ground.) spanner No.13 3 2 c Fig. 19: Strut installation Fig. 20: Installation of further supports. Fig. 18: Assembly using special bolts. Fig. 17: Assembly using special bolts. Special nut for rails rail M8x12 bolt with allen head L strut

Secure the support structure either by screwing it into

the roof, or applying a burden. In no event the permissible roof load shall be exceeded. Consulting a statics expert in advan­ ce is necessary. A damaged roof must be re- insulated by a specialist. Fix the collectors to the rails in the same man­ ner as if installing on an inclined roof (see point 2.4). Minimum distance between collector arrays see Fig. 22. Flat roof mount up to 8m high roof 1 collector 290 kg 2 collectors 580 kg 3 collectors 870 kg 4 collectors 1160 kg 5 collectors 1450 kg Fig. 21: Static safety (burden) twice the height winter sun solar collector height 25° solar collector Fig. 22: Minimum distance between collector arrays

5.1 - Connecting the collectors

For collector mounting follow the instructions in chapter 5.2. Fasten the first collector and lay the following one next to the first one, maintaining a sufficient gap. Then put the threaded fittings on both the upper and lower outlets and push the collector to the already mounted one until stop. Hold the fitting with a spanner (Fig. 24) to prevent turning, and tighten the nuts. Continue in the same way with further collectors. Put the insulation on the threaded fittings only after a successful leak test. 5.2 - Interconnecting the collectors Hydraulic interconnection of collectors shall be done according to Fig. 23a. Maximum of 5 collectors may be connected with threaded fittings in a row. If there are more than 5 collectors in a row, a compensator shall be installed in the middle of the array. With a compensator, max. of 10 collectors in a row may be installed. The con­ necting pipes shall be lead the shortest way. The recom­ mended pipe diameters and flow rates through collector arrays are shown in Tab. 1. Collectors may be also connected as shown in Fig. 23b. This kind of connection is permitted when up to 3 collectors are used and the max. flow rate is 1 l/min/ collector. Then the cold liquid inlet is at one side bottom and the hot liquid outlet is at the same side top. Both the other ends shall be plugged.. A brass elbow shall be installed at the inlet to the collec­ tor array with a transition to the interconnection piping. At the outlet from the collector array, a brass pipe cross shall be installed that will enable connection to collector piping. The brass elbow, pipe cross and plugs are invol­ ved in Regulus connection kit, code 7710. All solar components must be carefully and safely sea­ led and must be made of material resistant to glycol and temperatures up to 160 °C. For connection piping we recommend using KOMBIFLEX stainless-steel flexible pipes, or copper pipes joined by soldering. 5. HYDRAULIC CONNECTION Fig. 23a: The recom­ mended method of collector intercon­ necting Fig. 23b: Alternative one-sided connection method Fig. 24: Col­ lector con­ necting (the pic. shows connection of the upper fitting; the lower fitting shall be connected and tighte­ ned in the same way.)

Connection type Max.

recomm. flow rate Connecting pipe Copper Kombiflex array x collector 1 1 × 1 2 l/min Cu 15 × 1 DN 12 2 1 x 2 series 4 l/min Cu 15 × 1 DN 16 3 1 x 3 series 6 l/min Cu 18 × 1 DN 16 4 1 x 4 series 8 l/min Cu 18 × 1 DN 20 5 1 × 5 series 10 l/min Cu 22 × 1 DN 20 6 2 × 3 parallel 12 l/min Cu 22 × 1 DN 25 8 2 × 4 parallel 16 l/min Cu 28 × 1,5 DN 25 9 3 × 3 parallel 18 l/min Cu 28 × 1,5 DN 25 10 2 × 5 parallel 20 l/min Cu 28 × 1,5 DN 25 12 3 × 4 parallel 24 l/min Cu 28 × 1,5 - Max. 30 m of the inlet and outlet piping together. Fig. 26: Position of a temperature sensor In no event plastic tubes can be used for inlet/outlet piping as they do not meet the operation requirements for solar systems. Pipes for collectors can be lead through disused chim­ neys, ventilation shafts or grooves in a wall. In order to prevent high thermal losses through convection, open shafts shall be properly sealed. Also thermal dilatation shall be remembered and pipes fitted with compensators or other compensation elements. Piping shall be connected to the house earthing. Pipes of the solar system must be fitted with thermal insulation e.g. of SOLARFLEX type, so that thermal dissipation from the pipes does not deteri­ orate a total efficiency of the solar system. The thermal insulation must be resistant to temperatures up to 160 °C, for outdoor piping also a UV protection is essential as well as non-deliquescence of the material. For indoor piping, the thermal insulation should be at least 13 mm thick, for outdoor piping at least 19 mm. Place the thermal probe into the pocket X-piece at the outlet from the last collector, see pic. 26. A twisted wire 2x1 mm2, non-shielded should be used, separated from power cables. Its maximum length is 100 m. Minimize the number of electrical boxes a terminal blocks. connection length: up to 25 m cross section: 0.25 mm2 connection length: up to 50 m cross section: 0.5 mm2 connection length: up to 100 m cross section: 1.0 mm2 • the thermal and mechanical resistance of the wire used shall correspond to the environs the wire passes through. 6. TEMPERATURE SENSOR POSITIONING Tab. 1: Recommended pipe diameters AV23 Flow rate regulator with indicator 2-12 l/min, 3/4“ 3/8” air discharge valve and 3/8” ball valve up to 160°C Fig. 25 Possible collector connections

The pump station shall be installed in accordance with

the respective manual. Regulus pump stations contain the principal components shown in Fig. 27: 1 - Ball valve on flow line (red frame thermometer, 0-120 °C dial), with check valve 2 - Ball valve on return line (blue frame thermometer, 0-120 °C dial), with check valve 3 - Safety unit protects the installation from overpressure. It involves a 6 bar safety valve, manometer and G ¾” connection to expansion tank. 7. SOLAR PUMP STATION 4 - Air eliminator 5 - Circulation pump 6 - Flow control screw 7 - Filling valve 8 - Flowmeter 9 - Drain valve 10 - Safety valve spillway connection Safety valves are always included in pump stations. If no pump station is used in the installation, the solar system shall be equipped with a 6 bar safety valve, resistant up to 160 °C. No shut-off valve shall be installed between a safety valve and collectors. Fig. 27: Solar Pump Station 1 2 3 4 5 6 7 8 9 10

(Tab. 2 is valid for height up to 20 m only, otherwise the

size shall be calculated.) 8.1 - Expansion vessel sizing A solar expansion vessel shall be sized for a temper­ ature difference between the min. winter temperature and the max. summer temperature. The working range of expansion vessels is from -10 °C to +130 °C. Further it shall be able to contain fluid volume of all collectors in case of stagnation (max. collector temperature at no flow and high sunshine intensity). In solar systems with forced circulation such pressure expansion vessels shall be only used that are fitted with a propylene-glycol resistant membrane and whose min. working pressure is at least 6 bar. Installation shall be done in a position with the diaphragm flooded. In case the hear carrier starts boiling, the diaphragm mustn’t get in touch with steam! The recommended size of an expansion vessel see Table 2. Tab. 2: Expansion vessel recommended size. Max. 30 m of the inlet and outlet piping together. 8.2 - Calculation of a system working pressure The pressure in the solar system is calculated using the relation p = 1.3 + (0.1 h) p…pressure in a solar system [bar] h…height from a pressure gauge to the middle of a col­ lector field [m] Adjust the pressure by discharging solar liquid after the pressure test is done. 8.3 - Calculation of expansion vessel preset pressure Before filling the system, adjust the initial overpressure in the expansion vessel to a value by 0.5 bar below the calculated system pressure. p exp = p - 0.5 [bar] In order to set the pressure, use a current car-tyre pres­ sure gauge of a suitable pressure range. The expansion vessel has a current tyre valve under its lid. 8.4 - Examples of calculating working pres­ sure and expansion vessel pressure 8.4.1 - An example of calculating system working pressure The height from a pressure gauge to the middle of a collector: h = 10 m Pressure in the solar system (the solar system is to be pressurized to this value): p =1.3 + (0.1 h) = 1.3 + (0.1 . 10) = 2.3 bar 8.4.2 - An example of calculating expansion vessel pressure Before filling the system, the preset pressure in the expansion vessel shall be adjusted to the value of: p exp = p - 0.5 = 2.3 - 0.5 = 1.8 bar Number of collectors Expansion vessel size Max. piping length 3 18 Max. 30 m of the inlet and outlet piping together 4 25 5 40 6 50 8 50 9 80 10 80 12 100 8. EXPANSION VESSEL SIZING AND WORKING PRESSURE CALCULATION Fig. 28: Expansion vessel

Install the air vent to the highest point of the system.

Should there be more places with a risk of air pockets, air vents should be installed also there. It is recommended to amend the air vent with a local pipe widening that calms down the stream and helps in good separating bubbles from the fluid (see Fig. 30). A ball valve shall be always installed under the auto­ matic air vent valve, so that the automatic air vent can be closed after the system commissioning. Solar liquid leaks can be avoided in case of system stagnation. For an efficient removal of bubbles from the system it is advisable to fit the pump station with an air eliminator (see Fig. 29). 9. INSTALLATION OF AIR RELEASE VALVES Fig. 29: Air eliminator Fig. 30: Horizontal air eliminator and an automatic air eliminator

The below listed procedures are valid when a Regulus

pump station is used. 10.1 Filling • for safety reasons, you should only fill the collectors when there is no direct irradiation from the sun (or cover the collectors) • in order to fill the system, use a filling device with a reservoir for solar liquid and a filling pump (see Fig. 31) • attach the filling hose to the feed valve and open the valve completely • please use antifreeze solar fluid Regulus - Solarten Super to fill the system • attach the return hose to the bleed valve and open the valve completely • close the integrated ball valve in the flowmeter (the groove in the flowmeter‘s adjusting screw must be horizontal). • open the check valve (valves - two for a twin-pipe solar pump station) above the pump by turning the ball valve by 45° (intermediate position between open and closed) • pour sufficient quantity of solar fluid into the reservoir of the filling device, turn on the filling pump and fill the solar system. 10.2 Flushing • flush the solar system for at least 15 minutes using the filling device. In order to bleed air and possible impurities from the system perfectly, open shortly the integrated ball valve of the flowmeter from time to time (the groove vertically). 10.3 Air bleeding • with the filling pump running, close the bleed valve and increase the pressure up to about 5 bar • close the feed valve and turn off the filling pump, open the regulation screw on the flowmeter (groove horizon­ tally), do not disconnect the filling pump hoses! • set the circulation pump(s) to the highest speed and repeat switching on and off to air-bleed the system (an air-free pump works almost noiselessly) • watch the system pressure and when it starts falling, increase it by turning on the filling pump and opening the feed valve to 5 bar • repeat air bleeding so long until the float in the flowme­ ter‘s regulation valve takes a steady position during pump operation and bubbles stop appearing in the flowmeter. After that, let the circulation pump run for at least 5 minutes. 10. SYSTEM FILLING, FLUSHING, LEAK TEST AND AIR BLEEDING • in case an automatic air vent/s is/are used anywhere in the solar system, close this valve after air bleeding. 10.4 Leak test • examine the whole system at 5 bar pressure (all con­ nections, solar collectors, valves etc.), no visible leaks are allowed. Leave the system under pressure for at least 2 hours, then examine the system once again • consider the test result successful if no leaks appear and/or no noticeable pressure drop appears in the system • set the working pressure by point 8.2 Calculation of system working pressure • set the pump to a suitable speed and set the flow by the flowmeter and data in Tab. 1 • disconnect the hoses of the filling device and screw caps on the feed and bleed valves • open entirely the ball valve(s) above the pump • after several days of operation, air-bleed the system again. Do not flush the system with water. Since it is impossible to empty it completely, a risk of frost damage appears. Fig. 31: Filling a solar system

• Adjust the solar controller.

• Select an appropriate hydraulic variant in the controller menu. Check the controller settings and adjust parame­ ters. During solar controller setup, activate the re­ spective safety functions (collector protection, night recooling). 11. COMMISSIONING • uncover the collectors • place a sufficiently sized vessel (to hold the entire solar fluid volume) under the safety valve spillway • check if the circulation pump switches when the preset temperature difference between solar collectors and secondary circuit is reached The solar system offers unmanned and almost main­ tenance-free operation. Despite that, it is important to check the right functioning of the system within the first days of operation. First of all the temperature, system pressure and pump operation shall be checked. Once a year, preferably during a sunny day, it is necessary to check the working order and tight fixing of the collectors, verify the system tightness and pressure (incl. pressure in the expansion vessel) and the pump operation. At least once in every 2 years the heat carrying fluid shall be checked for its antifrost properties. The system shall be always replenished with the same fluid as the original filling was. The system must not be replenished with water. Always use solar liquid supplied by Regulus. Service or maintenance of the appliance may be done exclusively by an authorized person, holder of a valid authorization issued by Regulus, spol. s r.o. Regulus offers warranty for this product under the condi­ tions specified in the Warranty Certificate. The Warranty Certificate is an integral part of the documents supplied with the product. In case you wish to claim warranty, please contact your system supplier - installer. 12. OPERATION, CHECKS AND MAINTENANCE 13. SERVICING AND WARRANTY

Dimensions and Weight

height × width × thickness 2037 × 1036 × 90 mm connection width 1086 mm total area 2.110 m2 aperture area 1.907 m2 absorber area 1.887 m2 empty weight 38 kg Glass material tempered prismatic glass thickness 3,2 mm Absorber material aluminium, thickness 0.5mm surface finish Cermet design harp type, laser welded connection pipes material copper connection pipes dimension 4 × Ø 22 mm × 0.7 mm absorber tube material copper absorber tube dimension 9 × Ø 8 mm × 0.5 mm max. working pressure 10 bar max. working temperature 110 °C stagnation temperature 200 °C heat carrier solution of monopropylene glycol in water, 1:1, 1.40 l recommended flow rate 60 – 120 l/h Thermal Insulation material mineral wool insulation thickness 40 mm Frame material aluminum alloy color RAL 7039 back plate zinc-plated sheet iron , 0.5 mm thick Momentary efficiency per aperture / absorber area η0a 0.777 a1a 4.35 W/m2K a2a 0.0073 W/m2K2 tested by ISO 9806:2013 14. DATA SHEET FOR KPS1 SOLAR COLLECTOR

Graf tlakové ztráty kolektoru

Graf účinnosti kolektoru přes plochu apertury Momentary collector effi ciency over the aperture area for 1000 W/m2 insolation. KPS1 Collector power output in zero point for G=1000 W/m2 is 1481 W. Collector pressure drop Diagram of collector power output

16. DESCRIPTION OF PROCEDURES FOR ANNUAL PREVENTION CHECKS

Warning: Prevention examination and eventual intervention may be carried out by a qualified person only. Any work on electric wiring may be done by an authorized electrician only.. Maxi­ mum care shall be taken during checks. In case the procedure requires a person to get on a roof, a fall arrest is necessary. Check procedures Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Check the pressure in expansion vessel, replenish if necessary       Check system visually for leaks       Check the collector glazing cleanness, wash if necessary       Check ambient trees for possible shading       Check pipe insulation       Check the proper flow rate       Check temperature probes       Check the quality of antifreeze liquid (with a refractometer)*       Check the heat carrier pressure, replenish if necessary       Check the controller settings       Check for possible error messages in the controller and their reason       Check wiring       Check backup heating function (el. heating rod, gas-fired boiler)       Check the magnesium anode rod in the tank, substitute if necessary (see Instruction Manual)       Check the function of all system valves and fittings       Check the collector fixing       If needed, check the pressure in the heating system expansion vessel       If needed, clean the filter and de-aerate the heating system       Preventive training in system maintenance and controller setting for the operating staff       *If the test result shows the necessity, fill new heat carrier.

This Service Action Form is intended to register service intervention done. Entries may be recorded by an authorized

servicing company only. 17. SERVICE ACTION FORM This Service Action has been carried out by an authorized servicing company Date of Service Action: ..………………………………………………………………………………. Name of the servicing company: …………………….……………….………………...……….………………. Address of the servicing company: ………………………………………………………………………………… ………………………………………………………………………………… ………………………………………………………………………………… Name of the servicing person: .………………………………………………………………….……………. Contact phone: …….………………………………………………………………………….. Description of the intervention: .…………………………………………………………………………….…. .……………………………………………………………………………….. .……………………………………………………………………………….. ………………………………………………………………………………... ………………………………………………………………………………… ………………………………………………………………………………… ……..……………………………………………...………………………….. ………………………………………………………………………………… Signature of the person who has carried out the service action: ...............….…………………………………….. This Service Action has been carried out by an authorized servicing company Date of Service Action: ..………………………………………………………………………………. Name of the servicing company: …………………….……………….………………...……….………………. Address of the servicing company: ………………………………………………………………………………… ………………………………………………………………………………… ………………………………………………………………………………… Name of the servicing person: .………………………………………………………………….……………. Contact phone: …….………………………………………………………………………….. Description of the intervention: .…………………………………………………………………………….…. .……………………………………………………………………………….. .……………………………………………………………………………….. ………………………………………………………………………………... ………………………………………………………………………………… ………………………………………………………………………………… ……..……………………………………………...………………………….. ………………………………………………………………………………… Signature of the person who has carried out the service action: ...............….…………………………………….. This Service Action has been carried out by an authorized servicing company Date of Service Action: ..………………………………………………………………………………. Name of the servicing company: …………………….……………….………………...……….………………. Address of the servicing company: ………………………………………………………………………………… ………………………………………………………………………………… ………………………………………………………………………………… Name of the servicing person: .………………………………………………………………….……………. Contact phone: …….………………………………………………………………………….. Description of the intervention: .…………………………………………………………………………….…. .……………………………………………………………………………….. .……………………………………………………………………………….. ………………………………………………………………………………... ………………………………………………………………………………… ………………………………………………………………………………… ……..……………………………………………...………………………….. ………………………………………………………………………………… Signature of the person who has carried out the service action: ...............….……………………………………..

©2018 We reserve the right to errors, changes and improvements without prior notice.

REGULUS spol. s r.o. E-mail: [email protected] Web: www.regulus.eu v1.1-04/2019