INSTALLATION AND OPERATION INSTRUCTION
DYNAMIC BALANCED
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 1 -
FlowCon ABM 15-40mm, 1/2”-1 1/2”
Figure 1
Install the FlowCon ABM as called for in the de-
sign drawings. Although the performance of the
valve is not affected either way, industry stan-
dards call for balancing devices to be installed
on the downstream side of the terminal unit.
Especially for the ABM with its Optimizer® ball
valve, it is recommended to ensure the ball valve
is downstream of the balancing device.
INSTALL THE VALVE HOUSING WITH THE
FLOW DIRECTIONAL ARROW POINTING IN
THE CORRECT DIRECTION.
The FlowCon ABM valve is available with dou-
ble union end connections, i.e. figure 1.
Two types of end connections are available for
use with the union nut:
Threaded (male or female):
The thread standard is ISO 228, which is a
straight metric thread (compatible with BS-2779)
or NPT threading standard, depending on the
end connections ordered. The threads on both
the connection and piping should be cleaned
carefully. As these models are union end con-
nected, the union nuts and the end connections
should be removed for installation.
O-rings are supplied with the valve body and
used to seal the connections. It is recommended
to grease the o-rings with silicone grease before
installation. IMPORTANT: Never use mineral
oil or petrol based grease or oil on the o-rings.
Please make sure these are in place in the o-ring
grooves in the inlet and outlet of the valve body,
when installing the housing and REMEMBER
TO TIGHTEN THE UNION NUTS TO ENSURE
SEALING.
For all thread connections please clear threads
on both valve and piping of debris. Sealant such
as pipe dope or teflon tape is recommended.
WHEN USING HEMP AS PIPE SEALANT, EN-
SURE NO STRANDS ARE LEFT IN THE VALVE
OR PIPING.
Soldered end:
REMOVE THE END CONNECTIONS FROM
THE HOUSING BEFORE SOLDERING. THIS
ENSURES THAT THE O-RINGS AND INTER-
NAL PARTS ARE NOT DAMAGED BY HEAT.
Pressure/temperature fittings (p/t plugs) are
available upon request for the ABM valve. Be-
fore finger mounting the p/t plugs in the body
tappings, please seal the threads of the p/t plugs
(DO NOT OVER TIGHTEN).
Alternatively to the p/t plugs, the valve body can
be ordered with plugs for the body tappings.
Each plug is sealed by a gasket.
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 2 -
Figure 2
Figure 3
Actuators
The ABM valve should be installed so that the
actuator is located upwards and higher above
the valve center-line to prevent condensation
into the electronics. Valves are supplied in open
position.
Mechanical installation
1) Depress the clutch and manually close the
damper blades and position the actuator at 0°
or 90° so that the damper and the actuator co-
incide. NOTE: do not clutch the actuator when
the power is on.
2) Slide the actuator onto the shaft.
3) Tighten the nuts on the “U”-bolt to the shaft
with an 8mm wrench to a torque of 6.7Nm.
4) Slide the mounting bracket under the actua-
tor. Ensure free movement of the slot at the
base of the actuator. The bracket pin must be
placed in the mid distance of the slot.
Manual over-ride operation
1) DISCONNECT POWER. Failure to discon-
nect power may cause damage to the actua-
tor gears.
2) Fit the manual over-ride key onto the valve
spindle.
3) Press the clutch.
4) Rotate the manual over-ride key to open or
close the valve as required. CW will close the
valve and CCW will open the valve.
Actuator wiring
1) Remove the actuator cover by loosening the
cover screw.
2) Connect the wiring, pls. see figures 4-6.
Screw-terminals 6, 7 and 8 are only used on
actuators with end switches.
3) SW1 controls the direction of the rotation,
please see figures 4-6 for clock-wise (0 to 90°)
and counter-clock-wise (90 to 0°) rotation.
4) For actuators with end switches, the mechani-
cal auxiliary switches are fixed at 10° and 80°.
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 3 -
Figure 4
Figure 5
Figure 6
CLOSED 80-90
CLOSED 0-10
COMMON
COMMON (-)
22
SUPPLY (+)
-26VAC
28-32VDC
1
2
3 DRIVE CW
SW1
4
6
7
8
DRIVE CCW
24VAC - 2-position
24VAC - 3-POINT FLOATING
CLOSED 80-90
CLOSED 0-10
COMMON
COMMON (-)
22
SUPPLY (+)
-26VAC
28-32VDC
1
2
3 DRIVE CW
SW1
4
6
7
8
DRIVE CCW
COMMON (-)
SUPPLY (+)
22-26VAC / 28-32VDC
2-10VDC
1
2
3
24V - MODULATING 2-10VDC
24V - MODULATING 4-20mA
SW
JP1
Jumper at bottom
1
COMMON (-)
SUPPLY (+)
22-26VAC / 28-32VDC
4-20mA
1
2
3
SW
JP1
Jumper at top
1
CLOSED 80-90
CLOSED 0-10
COMMON
COMMON (-)
SUPPLY (+)
220-250VAC 50/60Hz
6
7
8
DRIVE CW
SW1
1
2
3
240V - 2-position
240V - 3-POINT FLOATING
CLOSED 80-90
CLOSED 0-10
COMMON
COMMON (-)
SUPPLY (+)
220-250VAC 50/60Hz
6
7
8
SW1
1
2
3
DRIVE CW
DRIVE CCW
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 4 -
Choice of insert
FlowCon ABM valves can be installed with either
a standard composite insert, internally adjust-
able to one of eight flow rates or the FlowCon
E-JUST insert, externally adjustable to one of 41
different flow rates in the same insert. Alterna-
tively, a factoryset stainless steel insert can be
installed with an adaptor.
It is recommended that the o-rings located
around the insert and adaptor are lubricated with
silicone grease, before the insert/adaptor is in-
stalled into the valve body. IMPORTANT: Never
use mineral oil or petrol based grease or oil on
the o-rings.
If the stainless steel insert needs to be ex-
changed, it is necessary to slightly cut the sides
of the grips on the adaptor with a box knife and
remove the insert by pulling the two now flexible
grips outwards on each side of the adaptor with
one hand and pulling the stainless steel insert
from the adaptor with the other. The o-ring will
come out as well.
Before installing the replacement insert, the
black composite part also needs to be replaced.
Simply remove the composite part using a small
piece of steel or brass bar or similar tool (ø10mm
and 150mm length). Place the ancillary tool
through the composite part and push down until
the part loosens a little; no need to use much
force. Then do the exact same thing from the op-
posite side of the part and the composite part is
now free and can be easily removed from the
brass head nut by hand.
The new composite part is placed into the brass
head nut. Please be aware of the two marks
on each side of the composite part; these must
fit into the two grooves on the brass head nut.
When in place, push the two parts together until
they click and the adaptor is ready for use.
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 5 -
Figure 7
D2
D1
A
E
B1
B2
B3
C
F
E
Assembly drawing FlowCon ABM
A:
Valve housing
B1:
E-JUST insert
B2:
Standard composite insert
B3:
Stainless steel insert w. adaptor
C:
Adjustment key
D1:
P/t plug (2 pcs.)
D2:
Plug and gasket (2 of each)
E:
Union end connections
F:
Actuator.
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 6 -
General
It is recommended flushing the system before
installing the insert in the valve body. Suitable
flushing caps are available. Water must always
be suitable treated, clean and free of debris. It is
recommended that a strainer be installed prior to
the valve body to prevent damage or blockage
due to debris. Ensure that the valve is not in the
fully closed position when filling the system with
water. Further it is recommended not to exceed
maximum differential pressure control range for
the insert, paricularly for the diaphragm type.
Warranty obligation
Failure to abide by all recommendations as per
this installation and operation instruction will void
warranty.
For latest updates please see www.flowcon.com
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 7 -
TEMPERATURE CONTROL VALVE
FlowCon ABM
1M95000ISO - 04/2016
FlowCon International assumes no responsibility
for mistakes, if any, in any printed material.
Denmark
Dubai
USA
Singapore
www.flowcon.com
- 8 -