Seakeeper 12HD Installation Manual
Read Online
Read the Seakeeper 12HD Installation Manual online using the built-in PDF viewer.
Text of the manual
*The Seakeeper 12HD is closely based on the Seakeeper 16. Because of this,
Seakeeper 16 drawings and part numbers are referenced in this Manual where
applicable.
Contents:
Section 1 – Mechanical Installation & PC-120 Guide
Section 2 – Electrical Installation
Section 3 – Cooling Installation
Section 4 – Startup
Section 5 – Installation Checklist and Required Supplies
44425 PECAN COURT, SUITE 151
CALIFORNIA, MARYLAND, 20619, U.S.A
PHONE: 410-326-1590
FAX: 410-326-1199
E-MAIL: [email protected]
1 of 21
Section 1: MECHANICAL INSTALLATION
1.0
Introduction
This document is intended to give details and guidance to a boat builder or equipment installer
to install the Seakeeper 12HD Stabilizing Gyro. The gyro is capable of producing loads up to
24.3 KN (5,450 lbs.) at each of the four mounts and careful consideration should be given to
foundation design to insure it is capable of transferring these loads into the hull.
There are two methods of installing the Seakeeper 12HD gyro:
1) Bolt-In Installation
2) Bond-In Installation
It is assumed that the installer is familiar with bonding using high strength adhesives or
mechanical fasteners to marine structures and has performed structural analysis to
assure the structure to which the gyro mounts can properly transfer the loads the gyro
creates into the hull structure. If the installer has any doubt about the ability of the
structure to transfer the gyro loads to the hull then he should contact a licensed naval
architect or marine engineer to do a structural analysis.
The installer should review the following list of reference drawings to ensure the installation
procedure is fully understood.
Reference Drawings
90364 Seakeeper 12HD Gyro Hardware Scope of Supply
90261 Seakeeper 16 Gyro Installation Details – Bolt in Method
90263 Seakeeper 16 Gyro Installation Details – Bond in Method
90305 Seakeeper 16 Gyro Cooling Water Schematic
90282 Seakeeper 16 Gyro Installation Template Kit
90306 Seakeeper 16 Gyro Cable Block Diagram
90309 Seakeeper 16 Gyro Bolt-in Installation Kit
FIGURE 1 – SEAKEEPER 12HD GYRO
2 of 21
Section 1: MECHANICAL INSTALLATION
1.1
Precautions
Gyro must only be lifted from the supplied lifting eyes (See Section 1.4).
Gyro flywheel is supported by precision bearings. Make certain while unpacking and
lifting gyro assembly to NOT drop or impart mechanical shock as damage to bearings
could result.
While handling / installing gyro assembly, protect exposed hydraulic brake cylinder rods
(See Figure 1) from scratches or damage as this could lead to premature seal failure
and oil leaks.
While handling / installing gyro assembly, do not allow electrical fittings that exit bottom
of gyro enclosure to come in contact with any surface or object as this could damage the
fittings and potentially affect the vacuum integrity of the enclosure.
Exercise care to protect gyro painted finish as damage to finish could lead to early
appearance degradation of installed gyro.
1.2
Selection of Gyro Installation Location
Selection of mounting location of gyro should consider the following desirable features:
The gyro must be installed aft of amidships to minimize high
acceleration loadings due to hull/wave impacts during operation at
high speed or in large waves.
Overhead access or sufficient clearance for removal / re-installation of gyro for
overhaul in future years.
Gyro should be installed in a dry space to minimize effects of corrosion.
Clearance for replacement of gimbal angle sensor on gyro gimbal shaft (see Figure 2).
Clearance for filling / purging brake hydraulic oil (see Figure 2).
Clearance for filling water/glycol cooling circuit (see Figure 2).
Clearance for replacement of brake hydraulic cylinders (see Figure 2).
3 of 21
Section 1: MECHANICAL INSTALLATION
VIEWS SHOWING RECOMMENDED CLEARANCES AROUND GYRO FOR USE OF HAND TOOLS, EASE OF
MAINTENANCE, INSTALLATION AND PROPER OPERATION.
FIGURE 2 – INSTALLED GYRO CLEARANCE CONSIDERATIONS
4 of 21
Section 1: MECHANICAL INSTALLATION
FIGURE 3 – TRANSVERSE BEAMS CLEARANCE CONSIDERATIONS
Refer to Figure 3 for recommended clearances to transverse beams. If a transverse beam is
located under the forward brace, it must be 1” (25 mm) from the edge of the gyro to provide the
necessary clearance for the swing of the motor power cable during gyro precession.
Clearances aft of the gyro are shown to provide access for maintenance.
5 of 21
Section 1: MECHANICAL INSTALLATION
Safety
There is a large torque about the gimbal axis when the gyro is precessing. Gyro
cover panels are provided to prevent personnel or equipment from contacting the
gyro while it is in operation. These covers should not be stepped on, or have
anything placed on top. The covers should always be in place during operation. If
it is ever necessary to access the gyro while the flywheel is spinning, the gyro
must be locked at the display to stop the gyro from precessing. Gyro
maintenance should not be attempted unless the gyro is locked and the flywheel
has stopped spinning.
The gyro should be treated with the same respect one gives a high speed rotating
propeller shaft or engine shaft.
Noise/Soundproofing
Gyro noise has been measured under steady state conditions (no wave load) in Seakeeper's
lab and in our test boat. The steady state noise is typically in the range of 68-70 dB un-
weighted. As the frequencies emitting the highest sound pressures are low (like other marine
machinery), it is recommended that the gyro be installed in a machinery space that is already
treated with soundproofing.
6 of 21
Section 1: MECHANICAL INSTALLATION
1.3
Selection of Installation Method
The Seakeeper 12HD gyro can be affixed to the hull structure using two methods 1) Use bolt-
in installation or 2) Bond-In installation. See figures below.
OPTION 1- DIRECT FASTENING OF GYRO FOUNDATION TO SHIPS STRUCTURE (BOLT-IN)
Option 1 would be applied when a metal structure is available for attachment. The foundation
would fasten directly to hull structure using isolation gaskets and 16x M14X2.0 fasteners.
Depending on the structure to which the gyro is fastened, blind threaded holes or thru-bolting
can be utilized.
OPTION 2- BOND-IN INSTALLATION (4 PLACES)
Option 2 would be most commonly used on a hull constructed of glass reinforced plastic (GRP)
or fiberglass. For this option, four 12.9 inch (327 mm) long by 4.9 inch (125 mm) deep saddles
are bonded to properly spaced and prepared structural members that are an integral part of the
hull structure. Seakeeper recommends using a structural adhesive with a lap shear strength of
2000 psi (13.8 MPa) or greater. Careful consideration should be exercised by the installer while
selecting the appropriate adhesive. Compatibility with the gyro’s cast aluminum A356- T6
saddles, hull structure and pot life are three important factors to consider. Proper surface
preparation in accordance with adhesive manufacturer’s recommendations prior to installation is
very important.
7 of 21
Section 1: MECHANICAL INSTALLATION
1.4
Unpacking Crate
1) Reference Seakeeper Drawing No. 90364, Seakeeper 12HD Gyro Hardware Scope of
Supply for items that ship with the gyro.
2) Remove electrical components, cables, and misc. items and set aside.
3) Remove packing materials that secure gyro assembly inside the crate.
4) Remove top and angled face cover panels to access lifting eyes
5) Attach spreader bar to the two lifting eyes located on the top of the gyro enclosure. Stay
clear of any other parts on the gyro. Gyro weighs 996 kg (2,195 lbs). See Figure 4
below.
FIGURE 4 – LIFTING ARRANGEMENT
Spreader Bar
Lifting Eyes
8 of 21
Section 1: MECHANICAL INSTALLATION
1.5
Bolt-In Installation
1.5.1 Check and Preparation of Hull Structure
Refer to Seakeeper Drawing No. 90261, Seakeeper 16 Gyro Installation Details – Bolt in
Method. Important dimensional and load information is given in this drawing that will impact the
design details of the structure that will receive the gyro. It is assumed that a proper structural
analysis has been performed for the hull structure to which the gyro will be fastened to insure
proper strength margins for the loads the gyro will create during operation.
The hull structure supporting the gyro should be installed so the gyro is parallel to the waterline.
In addition, the four areas on top of the beams on which the feet of the gyro foundation
and isolation gaskets will rest need to be co-planar within .06” (1.5 mm) to minimize
potential distortion of gyro support frame when installed.
Seakeeper provides an installation template kit, P/N 90282, which contains four plates that
mimic the mating surfaces of the four feet located on the gyro’s foundation. These plates have 4
holes located at the same centers as the mounting holes on the gyro. The fixture locates the
hole patterns at the proper spacing both in the fore-aft direction and the port-starboard direction.
See Figures 5 below. Once assembled, the fixture can be used to check clearances and
alignment of the hull structure.
Note: Do NOT use the installation fixture to establish gyro envelope dimensions. Refer
to Drawing No. 90261 for envelope dimensions. A 3-D model of the gyro is available on
the Seakeeper website (www.seakeeper.com) to aid in designing the gyro foundation and
the space around the gyro.
NOTE: MAKE SURE NO OBSTRUCTIONS FROM THE HULL STRUCTURE CAN BE SEEN WITHIN THE INSIDE
OF THE INSTALLATION TEMPLATE KIT (INSIDE THE MARKED RED LINES). REFERENCE SEAKEEPER
DRAWING NO. 90261.
FIGURE 5 –INSTALLATION FIXTURE
9 of 21
Section 1: MECHANICAL INSTALLATION
CAUTION: Tight clearances from cable guide bands to hull structure. See above figure
for dimensions and reference Seakeeper drawing NO. 90261 for complete gyro envelope.
10 of 21
Section 1: MECHANICAL INSTALLATION
1.5.2 Transfer of Holes to Boat Structure
1) Lower assembled fixture onto
hull structure.
2) The four areas where the feet
of the gyro will rest should be
coplanar to within .06”
(1.5mm). See Figure 10.
3) Align fixture in desired location
and transfer holes from fixture
plate to the hull structure. Note
that holes in fixture plate are
ø0.61 (15 mm).
4) Remove fixture and drill and tap
M14X2.0 holes in hull structure
at marked locations to mate with
holes in the gyro foundation.
Take special care to drill
perpendicular to mounting
surface. Remove any impeding
obstructions.
11 of 21
Section 1: MECHANICAL INSTALLATION
1.5.3 Installation of Gyro
1) Locate and position 4 isolation
gaskets onto foundation beams.
NOTE: Sealant or caulk is
recommended to be applied. Apply
a small bead (approximately 4mm
wide) of sealant (silicone or caulk)
between both mating surfaces of
each isolation gasket where it
contacts the beam and gyro. This
will prevent water from wicking
between the parts and setting up
corrosion. Check isolation gasket
alignment by test fitting bolts without
any obstructions.
2) Lower gyro into position onto the
hull foundation beams and align
over drilled holes.
3) Install Seakeeper supplied M14
fasteners– apply a moderate coat of
removable thread locker to the
threads of each bolt and include a
small bead of sealant under each
washer before installation.
4) Torque all fasteners to 100 ft-lbs
(136 N-m).
5) Proceed to electrical and cooling
portion of the installation.
12 of 21
Section 1: MECHANICAL INSTALLATION
1.6
Bond-In Installation
Seakeeper recommends a slow curing, non-sagging structural adhesive for bonding the saddles
to the GRP hull structure. Such an adhesive is Plexus MA590 which is a two-part methacrylate
adhesive. Details of the bonding procedure in this manual will involve the Plexus MA590
product, but that should not exclude other suitable adhesives the installer chooses to use. See
Sheet 6 of Seakeeper drawing no. 90263 for loads information and recommended
adhesive properties.
1.6.1 Initial Check and Preparation of Hull Structure
Refer to Seakeeper Drawing No. 90263, Seakeeper 16 Gyro Installation Details – Bond In
Method. Important dimensional and load information is given in this drawing that will impact the
design details of the structure that will receive the gyro as well as selection of the adhesive to
bond the gyro into the hull.
The foundation “saddles” of the gyro are designed to be bonded directly to the composite hull
structure of the vessel to effectively distribute gyroscopic loads. A complete bond is required
between the inside surface of the saddles and the hull structure. An estimate of adhesive
volume required should be calculated for each installation based on gaps between saddles and
structural members. There is some adhesive waste as a part of the process so a good rule of
thumb is to purchase 50% more adhesive than estimated volume to bond. Depending on
conditions and adhesive used, two workers may be required to apply the adhesive at the same
time to finish the installation before the adhesive starts to cure. To aid in determining the
quantity of adhesive required, the interior surface area (bonding surfaces) of each saddle is 164
in2 (1058 cm2) for a total bonded surface area for all four saddles of 656 in2 (4232 cm2).
The hull structure supporting the gyro should be installed so the gyro is parallel to the waterline.
The four areas on top of the beams that the saddles will bond to need to be co-planar
within .13” inches (3 mm) for consistent adhesive bond gap. In addition, the four areas
on top of the saddles on which the feet of the gyro foundation will rest need to be co-
planar within .06” (1.5 mm) to minimize potential distortion of gyro support frame when
installed.
Note that any paint or gel-coat present in bond area should be removed so that adhesive
will bond directly to laminate fibers and resin.
Seakeeper provides an installation fixture template, P/N 90282 that locates the saddles at the
proper spacing both in the fore-aft direction and the port-starboard direction. See Figures 6, 7 &
8 below. Once assembled with the provided saddle fittings, the fixture can be used to check
clearances and alignment of the hull structure. The fixture will allow the builder / installer to lay-
up and adjust the foundation dimensions to create a low-clearance fit between the gyro
foundation saddles and the hull structure. Shear strength of the adhesive will be maximized if
the cured thickness between the vessel structure and gyro saddles is at the thinner end of the
adhesive manufacturer’s recommended range. Therefore, the fixture should be used to confirm
13 of 21
Section 1: MECHANICAL INSTALLATION
that the overall dimensions of the foundations are square and level and that the adhesive gap is
within Seakeeper’s recommended range of 1 to 3mm (.04” to .13”).
Note: Do NOT use the installation fixture to establish gyro envelope dimensions. Refer
to Drawing No. 90263 for envelope dimensions. A 3-D model of the gyro is available on
the Seakeeper website (www.seakeeper.com) to aid in designing the gyro foundation and
the space around the gyro.
NOTE: MAKE SURE NO OBSTRUCTIONS FROM THE HULL STRUCTURE CAN BE SEEN WITHIN THE INSIDE
OF THE INSTALLATION TEMPLATE KIT (INSIDE THE MARKED RED LINES). REFERENCE SEAKEEPER
DRAWING NO. 90263.
FIGURE 6 – EXPLODED VIEW OF SADDLE INSTALLATION FIXTURE
14 of 21
Section 1: MECHANICAL INSTALLATION
FIGURE 7 – SADDLE INSTALLATION FIXTURE ON NOTIONAL HULL STRUCTURE
15 of 21
Section 1: MECHANICAL INSTALLATION
1.6.2 Fiberglass Hull Preparation
1) Position installation fixture (Fig 8) on hull girders noting recommended clearances for
maintenance from Figure 2. Check that the screws fastening the saddles to the
installation fixture are tight (Fig 6).
2) Mask hull area (Fig 9) around foundation saddles for easy clean-up and to create outline
of surface area to receive adhesive as (Fig 8). Insure that the bond gap is within the
adhesive manufacturer’s recommended thickness, or 3mm if using Plexus MA590.
3) Raise fixture clear of foundation. Check all four mounting areas are co-planar to within
.13” (3 mm) to each other, as well as parallel to the water line plane, as shown in Fig 8.
FIGURE 8 - INSTALLING FIXTURE ON HULL
FIGURE 9 - MASKING PERIMETER OF SADDLES
16 of 21
Section 1: MECHANICAL INSTALLATION
4) Thoroughly clean with alcohol or acetone all areas of girders to be bonded to remove
any contaminates. Use new paper towels for cleaning, not shop rags.
5) Remove any paint or gel-coat from bond surfaces so that adhesive will bond directly to
laminate fibers and resin as shown in Figure 8.
6) Thoroughly sand girder bond surfaces with 80 grit sandpaper. (IMPORTANT –
BOND STRENGTH MAY BE REDUCED IF THIS STEP IS SKIPPED.)
7) Wipe surfaces clean from dust with alcohol or acetone using new paper towels, not shop
rags.
8) Re-position installation fixture on girders and double-check that the adhesive gap is
within the adhesive manufacturer’s maximum recommended thickness. Seakeeper
recommends a maximum gap of 3mm if using Plexus MA590.
Note if bonding saddles to a metal structure, contact Seakeeper for
hull preparation instructions.
FIGURE 10 – COPLANAR PROPERTIES OF FOUNDATION
17 of 21
Section 1: MECHANICAL INSTALLATION
1.6.3 Gyro Saddle Preparation
1) Ensure that screws fastening saddles to the installation fixture are tight (Fig 6).
2) Check that each saddle contains 2 plastic screws which will insure an adhesive gap of
.080” (2 mm) on top surface of hull as shown in Figure 11.
3) Thoroughly clean with alcohol or acetone the inside surfaces of gyro foundation saddles
to remove any contaminates as shown in Figure 11. Use new paper towels for cleaning,
not shop rags.
4) Thoroughly sand all saddle inside surfaces with 80 grit sandpaper. (IMPORTANT
– BOND STRENGTH MAY BE REDUCED IF THIS STEP IS SKIPPED.)
5) Wipe surfaces clean from dust with alcohol or acetone using new paper towels, not shop
rags.
6) If using Plexus MA590 adhesive, apply Plexus PC-120 surface conditioner to inside
surfaces of gyro foundation saddles in accordance with manufacturer instructions.
These instructions are located at the end of this section. If using an alternate adhesive,
check with manufacturer if any surface conditioner/etch is required for the aluminum
saddles.
FIGURE 11 - SADDLE CLEANING
18 of 21
Section 1: MECHANICAL INSTALLATION
1.6.4 Bonding Saddles to Hull
Note: If using Plexus MA590 adhesive, the gyro saddles should be installed when PC-120 is
confirmed dry.
1) Assemble Plexus cartridge into either the manual or pneumatic gun as shown. Remove cap
on cartridge and attach mixing tip. For pneumatic gun, start with low air pressure and
increase until desired flow rate is achieved.
2) Cut tip of mixing wand as shown in photo.
3) Prepare a second mixing wand as shown in photo below by attaching the simple flexible
nozzle to the end of the mixing tip. Set aside for now as this will be used to inject adhesive
into the sides of each saddle after the fixture / saddles are in position.
4) Install provided rubber plugs in six holes of each
saddle. The plugs will limit the adhesive being forced
out of the injection holes in step 6 below.
Pneumatic Gun
Mixing Tip
Flexible Nozzle
Adhesive
Gun
Mixing Tip
19 of 21
Section 1: MECHANICAL INSTALLATION
5) Apply large bead of Plexus adhesive to
the hull structure as shown in the figure
to the right. Apply approximately 2/3rds to
1 cartridge at each of the four locations.
Work deliberate and fast as it takes
some time to apply the adhesive to the
structure. MA590 has a 90 minute
working time at room temperature (23°C
/ 73°F). This working time can reduce to
40-50 minutes at elevated temperatures.
Two workers should apply the adhesive
at the same time to finish the installation
before the adhesive starts to cure.
6) Lower fixture and saddles over the hull
structure and apply light downward
pressure to each of the four saddles until
the two nylon screws rest on the hull
structure (SEE FIG. 7). The adhesive
will be forced towards the forward and
aft ends of each saddle and partially
down the sides of the foundation beams.
7) Insert full adhesive cartridge along with
mixing wand / nozzle assembled in step
3 above into gun.
8) Begin to inject adhesive into the six
holes provided on each side of each of
the four saddles. Follow the numbered
sequence shown until the adhesive
pushes out the edges of the saddle
perimeter. The intent is to pump in the
adhesive working from the top down and
from the middle to the ends to fill the
gaps and displace any air.
A complete bond is required – excess adhesive will be needed to make sure
all bond gaps are filled.
20 of 21
Section 1: MECHANICAL INSTALLATION
9) Repeat above step for remaining 7 sides of the saddles.
10) When gaps have been completely filled, clean off excess adhesive, remove plugs, and
remove masking tape.
11) Allow adhesive to cure per manufacturer’s recommendations. Follow adhesive guidelines
for curing time versus temperature prior to removing the fixture.
12) Bonding of gyro saddles onto the hull is now complete. Remove installation fixture.
1.6.5 Installation of Gyro
1) The four areas where the feet of the gyro
will rest should be coplanar to within .06”
(1.5mm). See Figure 10.
2) Rig gyro for lifting and lower gyro into
position onto top surface of four saddles.
3) Apply a small bead (approximately 4mm
wide) of sealant or caulk to the mating
surfaces between the saddles and the gyro
foundation. Adjust position of gyro until
alignment is achieved for the 16 fasteners
that will attach gyro foundation frame to
saddles.
4) Install Seakeeper supplied M14 fasteners–
apply a moderate coat of removable thread
locker to the threads of each bolt and include
a small bead of sealant under each washer
before installation.
5) Torque all fasteners to 100 ft-lbs (136 N-m).
6) Proceed to electrical and cooling portion of
the installation.
21 of 21
Section 1: MECHANICAL INSTALLATION
1.7 Doc # 90213 Plexus PC-120 Application Instructions
Document #: 90213
Process: Plexus PC- 120 Application Instructions
Rev.: 1
Process Description: Instructions for use of surface conditioner
Page 1 of 4
What is Plexus PC-120?
•
Plexus PC-120 is a dual function primer/conditioner designed to clean surface contamination
and leave a thin coating of primer on specific metal surfaces.
•
Although designed specifically for cleaning and priming of Aluminum and Stainless Steel, PC-120
can be used to clean other surfaces in special situations. Contact Plexus Technical Service for
recommendations on any surface other than Aluminum or Stainless Steel.
Plexus PC-120 works by:
•
Cleaning the surface of contamination using Isopropyl Alcohol to “lift” machine oils and other
contamination.
•
Depositing a thin Phosphate based coating to retard corrosion.
•
Leaving a light “pink” color to assist in determining what areas have, and have not, been
treated with PC-120.
How should PC-120 be used?
•
PC-120 can be brushed, wiped or sprayed onto the surface being primed.
•
The PC-120 applied should then be wiped with a clean dry rag to remove any surface
contamination cleaned by the PC-120 and leave only a thin, quick drying film.
•
Dirty or oily rags should be replaced to avoid improper cleaning.
•
Quality dye-free paper towels that don’t leave fibers behind are recommended.
Common mistakes with PC-120
1) Using too much PC-120
2) Not removing the oils lifted off the metal surface before the PC-120 dries.
3) Not abrading corrosion that is already on the surface of the metal.
4) Using PC-120 past its shelf life.
Page 2 of 4
Product: ALL
Document #: 90213
Process: Plexus PC- 120 Application Instructions
Rev.: 1
1) Using too much PC-120
•
Only a very thin coat should be left on the metal. You should be able to see a slight “pink” cast
as illustrated below.
Too Much PC-120
Correct Amount
2) Not removing oils once primed
Wipe the surface with a dry rag
• The solvents in PC-120 will
clean and “lift” most
machining oils, but if the
metal isn’t wiped clean of
these oils then they will be
deposited right back onto
the metal surface when
the solvent in PC-120
evaporates!
• While still wet, wipe the
PC-120 applied to the
surface with a clean dry
paper towel, changing the
paper towel as needed.
Replace the rag when dirty
•
Notice how much aluminum oxide was cleaned off “clean” looking Aluminum
Page 3 of 4
Product: ALL
Document #: 90213
Process: Plexus PC- 120 Application Instructions
Rev.: 1
3) Not abrading corroded surfaces
•
As good as PC-120 is, it can’t help bonding performance if applied to a surface that is already
corroded!
•
Any surface that shows signs of corrosion should be cleaned by sanding or wire brushing to
remove any scale or corrosion.
•
After removal of corrosion then treat the surface with PC-120 as you normally would.
4) Using PC-120 past it’s shelf life
•
When stored under normal conditions PC-120 has a shelf life of 12 months in an unopened,
original container.
•
PC-120 bottles are marked with a lot number that is a simple 8 digit code that gives you the date
of manufacture.
o “807241” for example is 2008, 07 month (July), 24th day (the “1” refers to the first
batch of PC-120 made that day). Use the lot number to make sure the material is still
within shelf life.
•
Since it contains isopropyl alcohol, PC-120 should be tightly capped when not in use to stop
evaporation.
Page 4 of 4
Product: ALL
Document #: 90213
Process: Plexus PC- 120 Application Instructions
Rev.: 1
Remember these points! To avoid problems with Plexus PC-120:
•
Don’t use too much PC-120. Only a thin layer is needed.
•
Use a clean rag to wipe PC-120 off before it completely dries to remove surface contaminants it
has cleaned. Good quality paper towels are a better choice to minimize introduction of
contaminates to surface.
•
Any sign of corrosion already on the surface should be removed by abrading BEFORE priming.
•
Check the lot number for the date to make sure the PC-120 is less than a year old.
Questions
•
Please contact Plexus Technical Service at 1-800-851-6692 or [email protected]
1 of 1
Section 2: ELECTRICAL INSTALLATION
2.0
Introduction
This section for electrical installation explains how to mount the electrical equipment and how to
connect the electrical cables.
Reference Documents & Drawings
90364 Seakeeper 12HD Gyro Hardware
Scope of Supply
90371 Seakeeper 12HD Gyro Operation
Manual
90250 2nd Helm Control Station Kit
90306 Seakeeper 16 Gyro Cable Block
Diagram (includes 2nd Display Kit)
90337 Color Operator Display Envelope
and Mounting Details
SEAKEEPER 12HD Gyro, Front Oblique View
SEAKEEPER 12HD Gyro, Rear Oblique View
24VDC Power Connector Terminator, Female Tee Adapter
Color Display
Display Interface Cable
25m Cable
FIGURE 1 – ELECTRICAL EQUIPMENT FOR SEAKEEPER 12HD
CANvu 355 Display Interface Cable
20223
2 of 2
Section 2: ELECTRICAL INSTALLATION
2.1
Electrical Equipment Mounting
Precautions
Each item of electrical equipment has specific mounting instructions. These instructions
should be followed to insure proper function of the SEAKEEPER 12HD.
1. COLOR DISPLAY MOUNTING INSTRUCTIONS, SURFACE MOUNT
a. Console space required: Approx. 4.57 W x 4.57 H inches (116 x 116 mm)
b. Mounting Instructions, Surface Mount: See drawing 90337 for details
2. SERIAL COMMUNICATIONS TEE ADAPTER AND TERMINATOR MOUNTING
INSTRUCTIONS
a. Console space required, Rear: Approx. 4 W x 3 H inches (102 x 76 mm), rear
b. Mounting Instructions: Rear mount on vessel console panel, within 1 ft (0.3m) of
Display.
c. Hardware required: One mounting screw for .197” (5 mm) diameter mounting
hole on Tee Adapter.
Do NOT move Gyro mounted components from their
locations or incorrect Gyro operation will result.
3 of 3
Section 2: ELECTRICAL INSTALLATION
2.2
Electrical Equipment Power Connections
1. 230 VAC POWER SOURCE REQUIREMENTS
a. 230 VAC (nominal), 1 Phase, 50/60 Hz, 20 Amps.
b. A separate circuit breaker should be used for each Drive Box.
2. DRIVE BOX AC POWER INPUT CONNECTION INSTRUCTIONS
a. Cable: 3 x 10AWG (3 x 6mm2 CSA), 10’ (3m) length, Seakeeper supplied pre-
installed.
i. Locate CABLE 2 for AC power input to the Drive Box at the outward of three
cable glands.
FIGURE 2 – DRIVE BOX AC POWER INPUT & OUTPUT CABLE GLANDS
FIGURE 3 – CABLE 2 WIRE CONNECTIONS AT AC POWER DISTRIBUTION PANEL
OUTWARD CABLE
GLAND FOR AC POWER
INPUT
(CABLE 2)
MIDDLE CABLE GLAND
FOR AC POWER
OUTPUT TO
SEAWATER PUMP
(CABLE 5)
INWARD CABLE GLAND
FOR DRIVE POWER
OUTPUT TO GYRO
MOTOR
4 of 4
Section 2: ELECTRICAL INSTALLATION
ii. Connect 230 VAC wires in CABLE 2 to a 20 Amp, double-pole Circuit Breaker
at an AC power distribution panel according to Figure 3 above.
3. DRIVE BOX AC POWER OUTPUT TO SEAWATER PUMP CONNECTION
INSTRUCTIONS
a. Cable: 3 x 16AWG (3 x 2.0mm2 CSA) cable, 10’ (3m) length, Seakeeper supplied
pre-installed.
b. Pumps rated at 230 VAC, 5 Amps max., Customer-supplied.
c. Circuit breaker box, 2 pole, Customer-supplied
a. Locate CABLE 5 for AC power output to the Seawater Pump from the Drive Box at
the middle of three cable glands. (See Figure 2.)
FIGURE 4 – CABLE 5, AC OUTPUT POWER CABLE
b. Connect the AC output conductors in CABLE 5 to a 5 Amp maximum,
Seawater Pump according to Figures 4 and 5.
i. Pumps must be rated at 230 VAC, 5 Amps max., Customer-supplied.
The customer supplied seawater pump must have overcurrent protection with
a rating of 5A, 250 VAC. This protection circuit shall be installed in line with
the seawater pump as shown in the diagram below
FIGURE 5 – CABLE 5, WIRE CONNECTIONS TO SEAWATER PUMP
Verify that AC power is OFF to the Drive Box before connecting
CABLE 5 to a Seawater Pump.
5 of 5
Section 2: ELECTRICAL INSTALLATION
d. If the customer-supplied Seawater Pump is not rated for the applied AC input
voltage, the CABLE 5 output may be used to switch a customer-supplied relay.
i. Locate CABLE 5 for AC power output to the Seawater Pump from the Drive
Box at the middle of three cable glands as shown in Figure 2.
ii. The recommended wiring is shown in Figure 6. Refer to Figure 4 for Cable 5
wire connections.
FIGURE 6 – RECOMMENDED WIRING FOR SEAWATER PUMPS NOT 230 VAC
e. If CABLE 5 is not used, bundle cable and secure to forward brace or other area
nearby which will not come in contact with moving parts during gyro operation. Do
NOT cut CABLE 5 as it contains live voltage when gyro is in operation. Gyro
ships with CABLE 5 permanently sealed at end of cable with protective cap in the
event it is not used. Do NOT remove CABLE 5 from Drive Box as moisture will be
free to enter box through open cable gland and corrode internal electronic
components.
4. 24 VDC POWER SOURCE REQUIREMENTS
a. 24 VDC, 10 Amps.
b. A separate breaker should be used for each Gyro.
Cable 5 contains live voltage when gyro is in operation. Do NOT cut
Cable 5. Do not remove Cable 5 from Drive Box.
6 of 6
Section 2: ELECTRICAL INSTALLATION
5. GYRO DC POWER CONNECTION INSTRUCTIONS
Reversing polarity on the DC power input to the gyro can result in
damaging the electronics in the control system.
a. 24 VDC, 10 Amps. 2 x 12AWG (3 x 4mm2 CSA) Customer supplied.
i. Install Seakeeper provided DC Power Input Cable, P/N: 20248 as CABLE 1.
1. Route CABLE 1 to DC Power Distribution Panel.
2. Terminate RED conductor to +24 VDC. Terminate BLACK
conductor to 24V Rtn or Zero VDC.
ii. Before connecting CABLE 1 to gyro, check for proper voltage and polarity with
a DC multimeter using Figure 7 below.
iii. Connect CABLE 1 to 24VDC input receptacle on Gyro.
When energizing DC power the first time, if display does not power
up immediately then disconnect and inspect connector polarity.
2
1
FIGURE 7 – DC POWER INPUT CONNECTOR
CONTACT ASSIGNMENTS (front)
2
(24V Rtn)
1
(+24VDC)
7 of 7
Section 2: ELECTRICAL INSTALLATION
2.3
Electrical Equipment Ground Connections
1. GYRO TO VESSEL GROUND CONNECTION INSTRUCTIONS
a. Connect the Gyro foundation to vessel ground.
i. Install CABLE 6 (4AWG or 22.0mm2, Customer supplied) from the M6
brass ground stud on the Gyro rear brace to a suitable vessel ground.
FIGURE 9 – GYRO GROUND STUD ON REAR BRACE
GROUND
STUD
8 of 8
Section 2: ELECTRICAL INSTALLATION
2.4
Operator Station
This section explains the connection between the Operator Station equipment and the Gyro
Control Box.
Reference Drawing
90306 Seakeeper 16 Gyro Cable Block Diagram
1. DETERMINE LOCATION OF OPERATOR STATION
a. The desired location of the Operator Station must be determined with respect to
the vessel arrangement.
b. The operator display should be located on the bridge console.
c. Figure 10 below shows the CANbus communications link for the Operator
Station. The Terminator goes on one the far end of the Tee Adapter from the
Gyro.
FIGURE 10 – SERIAL COMMUNICATIONS LINK FOR OPERATOR STATION
2. ROUTE SERIAL COMMUNICATIONS CABLE
a. The CAN Cable Assembly (30243, CABLE 5) is a 25 meter shielded cable and
the largest connector is a molded plug with maximum outer diameter of .58 inch
(14.8mm).
b. CABLE 5 must be routed and installed in the vessel from the Gyro (female end)
to the Tee Adapter (male end) at the Operator Station.
Seakeeper SK Gyro CANbus Configuration, Single
New Display with bezel corners, Ship Monitor interface cable
CAN CABLE ASSY, 25m
SEAKEEPER
GYRO
F
F
F M
F
M
COLOR
DISPLAY
F
M
"SHIP MONITOR"
F
DISPLAY
INTERFACE
CABLE
TEE
ADAPTER
TERMINATOR,
FEMALE
M
"GYRO"
9 of 9
Section 2: ELECTRICAL INSTALLATION
3. INSTALL OPERATOR STATION EQUIPMENT
a. The Operator Station equipment is installed at the selected location using
Electrical Equipment Mounting Instructions in Section 2.1.
4. CONNECT OPERATOR STATION EQUIPMENT
a. The Operator Station equipment is connected in accordance with the Cable
Block Diagram, 90306.
10 of 10
Section 2: ELECTRICAL INSTALLATION
2.5
Second Operator Station Connection
This section explains how to connect the 2nd Operator Station Kit.
Reference Drawings
90250 Seakeeper 16 Gyro 2nd Operator Station Kit
90306 Seakeeper 16 Gyro Cable Block Diagram (includes detail of 2nd Operator Station)
1. DETERMINE LOCATION OF 2ND OPERATOR STATION
a. The desired location of the 2nd Operator Station must be determined with respect
to the 1st Operator Station and the vessel arrangement.
b. Typical locations include:
i. Flybridge
ii. Engine room
2. DETERMINE CABLING ARRANGEMENT
a. Figure 11 below shows the entire serial communications link for 2 Operator
Stations. The Terminator must be installed on the Tee Adapter farthest from the
Gyro.
FIGURE 11 – CABLING FOR 2 OPERATOR STATIONS
b. The Operator Station nearest the Gyro Control Box should be connected to
CABLE 5.
Seakeeper SK Gyro CANbus Configuration, Dual
New Display with bezel corners, Ship Monitor interface cable
SEAKEEPER
GYRO
F
F
F M
F
M
1st COLOR
DISPLAY
F
M
"SHIP MONITOR"
F
TEE
ADAPTER
M
"GYRO"
F
F
F M
F
M
2nd COLOR
DISPLAY
F
M
"SHIP MONITOR"
DISPLAY
INTERFACE
CABLE
TERMINATOR,
FEMALE
"GYRO"
CAN CABLE
ASSY, 25m
CAN CABLE
ASSY, 25m
TEE
ADAPTER
DISPLAY
INTERFACE
CABLE
11 of 11
Section 2: ELECTRICAL INSTALLATION
3. ROUTE 2ND OPERATOR STATION CABLE
a. A second CAN Cable Assembly (30243), also a 25 meter shielded cable, and the
largest connector is a molded plug with maximum outer diameter of .58 inch
(14.8mm)).
b. The additional CAN Cable Assembly must be routed in the vessel from the 1st
Operator Station (female end) to the 2nd (male end) Operator Station.
4. INSTALL 2ND OPERATOR STATION EQUIPMENT
a. The 2nd Operator Station equipment is installed at the determined location using
Electrical Equipment Mounting Instructions in Section 2.1.
5. CONNECT 2ND OPERATOR STATION EQUIPMENT
a. The 2nd Operator Station equipment is connected in accordance with the Cable
Block Diagram, 90306.
12 of 12
Section 2: ELECTRICAL INSTALLATION
2.6
Display Installation Template
The following template is for mounting; before using this template, measure to ensure
that the shown size is actual.
DISPLAY MOUNTING TEMPLATE
1 of 5
Section 3: COOLING INSTALLATION
3.0
Introduction
The Seakeeper 12HD is shipped with the cooling circuit filled and ready for use. Only a quick
confirmation of glycol level is required.
Reference Drawings
90364 Seakeeper 12HD Gyro Hardware Scope of Supply
90306 Seakeeper 16 Gyro Cable Block Diagram
90305 Seakeeper 16 Gyro Cooling Water Schematic
FIGURE 1 – SEAKEEPER 12HD
2 of 5
Section 3: COOLING INSTALLATION
FIGURE 2 – SEAKEEPER 12HD GYRO COOLING COMPONENTS
3 of 5
Section 3: COOLING INSTALLATION
3.1
Precautions
Installer is responsible for supplying a dedicated sea water pump and associated
plumbing. Sea water connections on the gyro heat exchanger mate with ¾ inch (19 mm)
hose.
There is no need to disconnect hose from glycol pump except to replace the pump. In
this case, provision will need to be made to catch draining glycol as plumbing is
disconnected. Use caution to avoid breaking plastic hose connections on pump casing.
An output is available from motor drive to power and automatically control seawater
pump. This pump must operate on 230 VAC single phase and consume less than 5
amps. Pumps requiring other voltages or higher current can still be controlled by using
this supply from motor drive to trigger an installer-supplied contactor but a separate
source of power must be provided.
Maximum sea water pressure in heat exchanger is 20 psi (1.4 bar)
Seawater flow requirement through heat exchanger is 4 GPM (15.1 LPM) minimum
and 8 GPM (30.3 LPM) maximum under all operating conditions of the boat. When
sizing sea water pump, installer should factor in losses for raw water plumbing. In
addition to initial operation at dock, new gyro installations should be checked to be within
the flow requirements while vessel is at speed. Flows higher than 8 GPM (30.3 LPM)
could affect heat exchanger life.
3.2
Adding Coolant
1)
Cooling system is filled to proper
level when shipped, with a mixture of
50%
ethylene
glycol
and
50%
distilled water. Clear tube between
thermostat housing and reservoir
should be filled with green coolant
mixture. If level has dropped, check
for
evidence
of
leaks
at
all
connections before adding fluid as
described below. If coolant is at the
correct level, skip to sea water
connection in section 3.3.
FIGURE 3 – SEAKEEPER 12HD COOLANT LEVEL
Correct Coolant Level
4 of 5
Section 3: COOLING INSTALLATION
2)
Mix 50% ethylene glycol with 50% distilled water in a clean container. Refer to Table 1
or glycol manufacturer’s literature for freezing points.
Table 1: Freezing Point
Ethylene Glycol Solution
(% by volume)
0
10
20
30
40
50
60
Temperature
(oF)
32
23
14
2
-13 -36 -70
(oC)
0
-3
-8
-16 -25 -37 -55
3) Remove pressure cap on top of reservoir. Pour mixture in until level reaches top of clear
tube between thermostatic valve and reservoir as shown in Figure 3. Filling reservoir
above this level will not cause any damage but coolant may be expelled from pressure
relief port below cap due to normal thermal expansion of coolant.
4)
Connect 24 V to controller.
At the Display check for any ALARMS
Press the POWER ON/OFF button
The flywheel will start to spin and the glycol pump will start.
Recheck glycol level with fluid circulating in coolant circuit. Sight down inside
reservoir and check that coolant level is above upper port on reservoir as shown in
Figure 3. Replace cap.
After several minutes of running, press POWER ON/OFF button
to turn power
off to the flywheel and glycol pump. The glycol pump will stop and the flywheel will
coast to a stop.
5 of 5
Section 3: COOLING INSTALLATION
5)
The cooling system is self-purging. If small amounts of air are in the system, they will
most likely be dislodged during the first sea trial. Recheck level after sea trial and add
fluid if required.
3.3
Connecting Seawater to Heat Exchanger
1)
Connect seawater from installer supplied pump to left 3/4” (19 mm) hose barb on heat
exchanger. Use the same practices as other below waterline seawater plumbing.
Required flow rate is 4 GPM (16 LPM) minimum and 8 GPM (30.3 LPM) maximum.
2)
Connect seawater discharge (right hose barb) to overboard drain. Use the same
practices as other below waterline seawater plumbing.
3)
In addition to initial operation at dock, new gyro installations should be checked for
minimum 4 GPM (16 LPM) flow while vessel is at speed and when backing down. If no
other method of confirming flow is available, discharge line may be temporarily diverted
to a bucket. Flow is calculated from time to fill a known volume.
4)
Inspect raw water plumbing after sea trial for any signs of leakage.
5)
Heat exchanger contains removable end-caps to provide access for cleaning the tube
bundle.
FIGURE 4 – SEAKEEPER 12HD SEAWATER CONNECTIONS
1 of 2
Section 4: STARTUP
4.0
Introduction
This section describes the first startup of the gyro.
Also reference Seakeeper Document # 90371, Seakeeper 12HD Gyro Operation Manual.
•
Previous sections for mechanical, electrical and cooling installation must
be completed before this startup sequence is initiated.
•
Before continuing, covers must be installed and the area around the gyro
must be clear of personnel and equipment!
4.1
Startup Instructions
1) Energize 24 VDC supply at the customer supplied electrical disconnect.
2) Supply 220 VAC to Motor Drive Box at customer supplied electrical disconnect.
3) If sea water pump for gyro is not supplied though cable from Motor Drive Box, turn on
the boat’s AC or DC circuit breaker that supplies power to the sea water pump.
4) With system powered up check the display for any ALARMS. If there are any ALARMS
present they must be corrected first.
5) Press the GYRO ON/OFF Button on Display.
The RED LOCK ICON and the
PROGRESS BAR will appear and be RED until the GYRO is at speed, then stabilization
can begin.
2 of 2
Section 4: STARTUP
6) The sea water pump should have started when the ON/OFF button on the display was
depressed. Confirm pump operation and flow rate, if practical. Required flow is 4 GPM
(15 LPM) minimum and 8 GPM (30 LPM) maximum.
7) Verify that there are no ALARMS present. If an ALARM is present it will be displayed.
8) When the PROGRESS BAR turns GREEN from RED the GYRO can be placed in SEA
mode. Depress the LOCK/UNLOCK Button
and the GYRO will be free to move
and precession can occur.
9) Verify that there are no alarms. If an ALARM is present it will be displayed.
10) Press the LOCK/UNLOCK Button
to go from SEA to LOCK mode. Then press
the GYRO ON/OFF Button
to power the GYRO down.
11) During normal operation, the gyro should be stopped when pulling into port and
stabilization is no longer required. This maximizes long term life as it allows the gyro to
start the coast down cycle before cooling is shutoff. Once the vessel is secured in the
slip and the crew has shut down the generator and engines, the AC and DC breakers
that control the gyro should be switched to the OFF position. The gyro will continue to
spool down to zero rpm. No cooling is required during this time. Note gyro may take 4+
hours to coast down to zero rpm from full speed. When the flywheel has stopped the
display will indicate 0 RPM.
1 of 4
Section 5: INSTALLATION CHECKLIST AND SUPPLIES
Please Complete Checklist and E-mail to [email protected]
or telefax to +1.410.326.1199
5.0
Installation Checklist
Mechanical Checklist (reference Installation Manual Section 1)
Gyro Foundation Installed in Hull
Foundation bolts torqued to specification
Electrical Checklist (reference Seakeeper Drawing 90306 & Installation Manual Section
2)
Mount Components
Display (near helm)
Connect Customer Supplied Cables
Cable 1
–
Connect other end of Cable 1 to 24 VDC power
at customer supplied connection box or directly
to circuit breaker
–
Plug connector of Cable 1 into mating
connector on gyro wire harness
Cable 6 (customer supplied) –
Install lugs on both ends of customer supplied
4AWG ground cable
–
Connect one end of Cable 6 to nearest vessel
ground and other end to gyro rear brace
Connect Seakeeper Supplied Cables
Cable 2 (Seakeeper supplied) –
Connect Cable 2 from Drive Box to 230 VAC
single phase at customer supplied connection
box or directly to circuit breaker
Cable 5 (Seakeeper supplied) –
Connect Cable 5 from Drive Box to customer
supplied Circuit Breaker Box and 230 VAC
seawater pump
2 of 4
Section 5: INSTALLATION CHECKLIST AND SUPPLIES
Cable 3 (Seakeeper supplied) –
Connect female end of CAN communications
Cable 3 to mating connector on gyro wire
harness
–
Route CAN communications Cable 3 from gyro
to helm (male end goes to helm)
–
Connect male end of CAN communications
Cable 3 at helm to CAN Tee Adapter
–
Connect Display and Seakeeper supplied Cable
4 to CAN Tee Adapter with CAN Terminator
Cooling Checklist (reference Installation Manual Section 3)
Verify coolant level in heat exchanger coolant reservoir.
Connect sea water hoses / open sea cocks to heat exchanger and test sea water
pump.
Verify 4 GPM (15 LPM) minimum and 8 GPM (30 LPM) maximum sea water flow
through heat exchanger under all operating conditions of the boat.
Startup Checklist (reference Installation Manual Section 4 and Operation Manual
Section 2)
Remove lifting bolts and Install cover panels
Turn on 24 VDC circuit breaker
Turn on 230 VAC circuit breaker
Verify display works and no alarms are present
Follow instructions in Section 4.1 of Installation Manual to turn on the GYRO
Verify sea water pump turns on when the GYRO is turned ON
Verify that no ALARMS are present
Follow instruction in Section 4.1 of Installation Manual to turn off the Gyro
AC & DC power and sea water pump may be turned off after the GYRO is turned
off by placing the GYRO in LOCK mode and Turning the GYRO off
Gyro takes 4.5+ hours to coast down to zero rpm from full speed
3 of 4
Section 5: INSTALLATION CHECKLIST AND SUPPLIES
5.1 Required Supplies needed for Gyro Installation (not supplied
with gyro)
Item Description
Qty
Installation
Manual
Reference
Section
Other
Reference
System
1
Adhesive and cleaning supplies for bonding to hull
1
Mechanical
2
Soundproofing Considerations
1
Mechanical
3
Spreader bar for lifting gyro
1
Mechanical
4
Hose clamps for seawater plumbing to 3/4" (19 mm)
hose barb (2 per hose barb)
4
3
Cooling
5
Cable, 2x14AWG or 2x12AWG, 24 VDC power input
to Gyro
AR
2.2.5
Dwg 90306
Electrical
6
Deutsch Crimp Tool HDT-48-00 or HDT-1561 (or
equivalent).
1
2.2.5
Electrical
7
M6 terminal lug for grounding gyro at rear brace
1
2.3.1
Electrical
8
Cable, 4AWG, for grounding gyro at rear brace to
vessel ground (used with item 7)
AR
2.3.1
Dwg 90306
Electrical
9
Sea water pump, 230V AC
1
2.2.3
Electrical
10
Relay for sea water pump control
(Not required if using 230V AC pump)
1
2.2.3
Electrical
11
Junction Box with 5 Amp, 2-Pole Circuit Breaker
(Not required if using DC distribution panel 12VDC
seawater pump)
1
2.2.3
Dwg 90306
Electrical
AR = As Required
Dwg = Drawing
4 of 4
Section 5: INSTALLATION CHECKLIST AND SUPPLIES
List of common tools that may be required for installation
Item
Description
Use
1
Wire cutter
DC Power, AC Power cables
2
Wire stripper
DC Power, AC Power cables
3
1/8 hex key
Gimbal sensor mount plate
4
2.5 mm hex key
Gimbal angle sensor
5
Slot screwdriver, 5/64 inch
Field assembly connectors
6
1/4 inch nutdriver
Hose clamps
7
Terminal or quick disconnect
crimper
Power cables
8
Utility knife
Scoring cable jackets