Digital Projection RIGGING FRAME Installation Manual
Text of the manual
Rev B March 2015
115-918B
HIGHlite 660 / 740 / 8000 Series
HIGHlite Laser 3D Series
M-Vision 930 Series
Titan LED / 800 / 930 / Quad Series
RIGGING FRAME INSTALLATION GUIDE
4
Rigging Frame Installation Guide
Rev B March 2015
About This Document
Follow the instructions in this manual carefully to ensure safe and long-lasting use of the rigging frame.
Symbols used in this manual
Many pages in this document have a dedicated area for notes. The information in that area is accompanied by the following symbols:
WARNING: this symbol indicates that there is a danger of physical injury to yourself and/or damage to the equipment unless
the instructions are closely followed.
ELECTRICAL WARNING: this symbol indicates that there is a danger of electrical shock unless the instructions are closely
followed.
NOTE: this symbol indicates that there is some important information that you should read.
Product revision
Because we at Digital Projection continually strive to improve our products, we may change specifications and designs, and add new features
without prior notice.
Legal notice
Trademarks and trade names mentioned in this document remain the property of their respective owners.
Digital Projection disclaims any proprietary interest in trademarks and trade names other than its own.
Copyright © 2015 Digital Projection Ltd. All rights reserved.
Notes
Rigging Frame Installation Guide
Rev B March 2015
Safety Information
Please follow the instructions in this document carefully to ensure a safe installation.
Please consider keeping the original box and packing materials in case you ever need to ship the frame.
Safety warnings
INTENDED USE
This rigging frame is intended for use by fully qualified, trained and competent persons as an aid to provide safe and secure
transportation, installation and adjustment of projectors.
Only use the frame indoors, where there is no wind.
This frame is intended for use only with the projectors listed in Which Products Are Compatible With This Frame? further in
this manual. Any attempt to use the frame with other projectors may result in severe injury or damage.
MAINTENANCE AND INSPECTION
The Rigging Frame is a maintenance free product. However, before carrying out an installation it is essential to ensure that:
• No screws are missing and all screws are in the right position.
• No screws, adjustment wheels or other components are damaged.
• No plates, square pipes or other components are bent or broken.
Use a suitable tool to test each screw and make sure that none are loose.
After an installation, ensure that all screws, washers and insulations are present and positioned correctly.
Notes
Rigging Frame Installation Guide
Rev B March 2015
INSTALLATION AND MOUNTING
Installation errors may lead to serious accidents.
Installation should only be carried out by qualified personnel.
Installation should be carried out by a minimum of two persons.
Do not place the projector on sloped or unstable surfaces as it may fall or tip over, resulting in injury or damage. Make sure
the surface can support a weight of 210 kg (462.97 lb).
Do not exceed the maximum weight loads for ceiling mounts. For suspended installations, use only designated hanging
accessories such as the truss mount and the 750 kg Doughty clamp for a maximum weight load of 138 kg (304.23 lb).
When stacking projectors, make sure all four threaded rods are tightened with a torque of 5 N m.
Do not position the frame in a manner which may impede projector ventilation. Poor ventilation may result in a fire. Ensure
that there is at least 30 cm (12 in) of space between the ventilation outlets and any wall, and 10 cm (4 in) on all other sides.
Prevent property damage and personal injury caused by incorrect installation. Ensure the frame is in good condition, the
installation has been carried out properly and the load capacity of the supporting structure is sufficient to carry the weight of
the entire installation, up to 150 kg (330.69 lb) incl. lenses, cabling, etc.
Do not operate the projector in humid or dusty places or in places where the projector may come into contact with oily
smoke or steam. Using the projector in such conditions may result in fire, electric shocks or plastic deterioration.
Notes
Rigging Frame Installation Guide
Rev B March 2015
SAFE HANDLING
Avoid injury from falling objects during assembly and disassembly of the frame. Wear protective shoes, gloves and helmet.
The frame is heavy. Use safe handling techniques when lifting the frame.
Wear safety gloves to prevent fingers being caught between the outer rings and the plates. When adjusting the image, keep
your hands on the adjustment wheels at all times as shown below. Do not lean on the frame.
Notes
Rigging Frame Installation Guide
Rev B March 2015
Which Products Are Compatible With The Rigging Frame?
The rigging frame can be used with the following projectors:
Products
Badges
• HIGHlite Laser 3D
HIGHlite
3D
LASER
• HIGHlite 660 and 740 2D
• HIGHlite 660 3D
• HIGHlite 8000
HIGHlite
2D
660
740
HIGHlite
3D
660
HIGHlite
2D
8000
• M-Vision 930 3D
M-Vision
3D
930
• Titan LED
LED
3D
• Titan 800 and Titan 930
2D
800
3D
800
2D
930
3D
930
• Titan Quad Series:
• Titan Quad
• Titan Super Quad / Quad 2000
2D
Quad
3D
Quad
2D
Quad
Super
3D
Quad
Super
2D
Quad2000
3D
Quad2000
Notes
Any attempt to use the frame with
other projectors may result in
severe injury or damage.
Rigging Frame Installation Guide
Rev B March 2015
IN THIS GUIDE
What’s In The Box?.............................................................................................. 1
Fitting HIGHlite Laser In The Frame............................................................. 2
Required parts..............................................................................................................2
Setup.............................................................................................................................2
Order of components in assembly with HIGHlite Laser...........................................6
Fitting M-Vision 930 In The Frame................................................................. 7
Required parts..............................................................................................................7
Setup.............................................................................................................................7
Order of components in assembly with M-Vision 930............................................11
Fitting Titan In The Frame.............................................................................. 12
Required parts............................................................................................................12
Setup...........................................................................................................................13
Order of components in assembly with Titan.........................................................16
Fitting HIGHlite In The Frame....................................................................... 17
Required parts............................................................................................................17
Setup...........................................................................................................................17
Order of components in assembly with HIGHlite....................................................21
Adjustment Options........................................................................................... 22
Roll..............................................................................................................................22
Pitch............................................................................................................................22
Yaw..............................................................................................................................22
Stacking Projectors.......................................................................................... 23
Ceiling Installation............................................................................................ 24
Ceiling installation using 750 kg / 1650 lb Doughty clamps..................................24
Safe fitting areas - bottom................................................................................................25
Safe fitting areas - top......................................................................................................26
Ceiling installation using the truss mount (optional accessory)..........................27
Adjusting ceiling installations with the truss mount..............................................28
Maximum Weight Loads................................................................................... 29
Truss mount installations..........................................................................................29
Ceiling installation using 750 kg / 1650 lb Doughty clamps..................................30
Table mounts..............................................................................................................31
Dimensions........................................................................................................... 32
Rigging frame.............................................................................................................32
Truss mount................................................................................................................33
Rigging Frame Installation Guide
WHAT’S IN THE BOX?
Rev B March 2015
What’s In The Box?
Notes
Make sure your box contains
everything listed. If any pieces are
missing, contact your dealer.
You should save the original box
and packing materials, in case you
ever need to ship the rigging frame.
The frame is shipped with all
components listed here. However,
some projectors do not use all
screws, sleeves and washers
supplied. To find out which parts you
need for your installation, refer to the
relevant projector section:
• Fitting HIGHlite Laser In The
Frame
• Fitting M-Vision 930 In The
Frame
• Fitting Titan In The Frame
• Fitting HIGHlite In The Frame
1 x rigging frame
115-919
4 x M10x25 low profile
socket head screws
115-921
4 x ø10 insulation washers
115-922
4 x ø10 insulation sleeves
115-923
6 x M6x20 button head screws
115-924
12 x ø6.2 insulation sleeves
115-925
4 x square to round adaptors
115-920
Rigging Frame Installation Guide
115-918
4 x ø10.5 insulation spacers
115-994
6 x ø6 spring lock washers
116-226
Rigging Frame Installation Guide
FITTING HIGHLITE LASER IN THE FRAME
Rev B March 2015
Fitting HIGHlite Laser In The Frame
HIGHlite
3D
LASER
Required parts
Part
Quantity
Rigging frame
1
M10x25 low profile socket head screws
4
ø10 insulation washers
4
ø10 insulation sleeves
4
M6x20 button head screws
6
ø6 spring lock washers
6
ø6.2 insulation sleeves
12
Setup
1. Remove the lens hood.
2. Place the projector upside down on a suitable flat surface and remove
the four adjustable feet 1 .
3. Place the ø10 insulation washers over each M10 screw hole 2 .
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
1
1
1
1
2
2
2
2
Rigging Frame Installation Guide
FITTING HIGHLITE LASER IN THE FRAME
Rev B March 2015
Setup (continued)
4. Insert six of the ø6.2 insulation sleeves in the M6 screw holes 3 on the inside of the frame.
Notes
This procedure requires two
persons.
.
It is important to use the sleeves
as they provide galvanic isolation.
3
3
3
3
3
3
Rigging Frame Installation Guide
FITTING HIGHLITE LASER IN THE FRAME
Rev B March 2015
Setup (continued)
5. Position the rigging frame over the projector so that the adjustment screws 4 are at the back, aligning the M10 5 and
M6 screw holes 6 .
Ensure that the projector plate 7 is flat against the body of the projector.
This can be achieved by placing the projector on a surface which is smaller than
the frame, allowing full contact between the plate and the projector.
Notes
This procedure requires two
persons.
.
4
4
6
5
5
6
6
5
5
6
6
6
7
Rigging Frame Installation Guide
FITTING HIGHLITE LASER IN THE FRAME
Rev B March 2015
Setup (continued)
6. Place the ø10 insulation sleeves over each M10 hole. Secure the four M10x25 low profile socket head screws 8 into each hole.
Ensure each screw runs through the corresponding sleeve and washer and catches into the corresponding M10 hole in the projector
surface.
7. Place the other six ø6.2 insulation sleeves over each M6 screw hole. Place a ø6 spring lock washer over each ø6.2 insulation sleeve.
Secure the six M6x20 button head screws 9 into each hole. Ensure each screw runs through the sleeve and washer and catches into
the corresponding M6 hole in the projector surface.
Notes
This procedure requires two
persons.
It is important to use the sleeves
and washers as they provide
galvanic isolation.
Torque: 4±0.5 N m.
8
9
8
9
9
8
8
9
9
9
Rigging Frame Installation Guide
FITTING HIGHLITE LASER IN THE FRAME
Rev B March 2015
Order of components in assembly with HIGHlite Laser
1
M10x25 low profile socket head screw
2
ø10 insulation sleeve
3
Projector plate
4
ø10 insulation washer
5
M6x20 button head screw
6
ø6 spring lock washer
7
ø6.2 insulation sleeve
Notes
1
2
3
4
5
6
3
7
7
Notes
This procedure requires two
persons.
It is important to use the sleeves
and washers as they provide
galvanic isolation.
Torque: 4±0.5 N m.
Rigging Frame Installation Guide
FITTING M-VISION 930 IN THE FRAME
Rev B March 2015
Fitting M-Vision 930 In The Frame
M-Vision
3D
930
Required parts
Part
Quantity
Rigging frame
1
M6x20 button head screws
6
ø6 spring lock washers
6
ø6.2 insulation sleeves
12
Setup
1. Place the projector upside down on a suitable flat surface and remove
the four adjustable feet 1 .
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
1
1
1
1
Rigging Frame Installation Guide
FITTING M-VISION 930 IN THE FRAME
Rev B March 2015
Setup (continued)
2. Insert six of the ø6.2 insulation sleeves in the M6 screw holes 2 on the inside of the frame.
Notes
This procedure requires two
persons.
.
It is important to use the sleeves
as they provide galvanic isolation.
2
2
2
2
2
2
Rigging Frame Installation Guide
FITTING M-VISION 930 IN THE FRAME
Rev B March 2015
Setup (continued)
3. Position the rigging frame over the projector so that the adjustment screws 3 are at the back, aligning the M6 screw holes 4 .
Ensure that the projector plate 5 is flat against the body of the projector.
This can be achieved by placing the projector on a surface which is smaller than
the frame, allowing full contact between the plate and the projector.
Notes
This procedure requires two
persons.
3
3
4
4
4
4
4
4
5
Rigging Frame Installation Guide
FITTING M-VISION 930 IN THE FRAME
Rev B March 2015
Setup (continued)
4. Place the other six ø6.2 insulation sleeves over each M6 screw hole. Place a ø6 spring lock washer over each ø6.2 insulation sleeve.
Secure the six M6x20 button head screws 6 into each hole. Ensure each screw runs through the sleeves and catches into the
corresponding M6 hole in the projector surface.
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
Torque: 4±0.5 N m.
6
6
6
6
6
6
Rigging Frame Installation Guide
FITTING M-VISION 930 IN THE FRAME
Rev B March 2015
Order of components in assembly with M-Vision 930
1
M6x20 button head screw
2
ø6 spring lock washer
3
ø6.2 insulation sleeve
4
Projector plate
1
2
4
3
3
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
Torque: 4±0.5 N m.
Rigging Frame Installation Guide
FITTING TITAN IN THE FRAME
Rev B March 2015
Fitting Titan In The Frame
LED
3D
2D
800
3D
800
2D
930
3D
930
2D
Quad
3D
Quad
2D
Quad
Super
3D
Quad
Super
2D
Quad2000
3D
Quad2000
Required parts
Part
Quantity
Rigging frame
1
M10x25 low profile socket head screws
4
ø10 insulation sleeves
4
ø10.5 insulation spacers
4
Notes
This procedure requires two
persons.
Rigging Frame Installation Guide
FITTING TITAN IN THE FRAME
Rev B March 2015
Setup
1. Place the projector upside down on a suitable flat surface and remove the four adjustable feet 1 .
2. Place the ø10.5 insulation spacers over each M10 screw hole 2 .
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
1
1
1
2
2
2
1
2
Rigging Frame Installation Guide
FITTING TITAN IN THE FRAME
Rev B March 2015
Setup (continued)
3. Position the rigging frame over the projector so that the adjustment screws 3 are at the back, aligning the M10 screw holes 4 .
Ensure that the projector plate 5 is flat against the body of the projector.
This can be achieved by placing the projector on a surface which is smaller than
the frame, allowing full contact between the plate and the projector.
Notes
This procedure requires two
persons.
3
3
4
4
4
4
5
Rigging Frame Installation Guide
FITTING TITAN IN THE FRAME
Rev B March 2015
Setup (continued)
4. Place the ø10 insulation sleeves over each M10 hole. Secure the four M10x25 low profile socket head screws 6 into each hole.
Ensure each screw runs through the corresponding sleeve and washer and catches into the corresponding M10 hole in the projector
surface.
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
Torque: 4±0.5 N m.
6
6
6
6
Rigging Frame Installation Guide
FITTING TITAN IN THE FRAME
Rev B March 2015
Order of components in assembly with Titan
1
M10x25 low profile socket head screw
2
ø10 insulation sleeve
3
Projector plate
4
ø10.5 insulation spacer
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
Torque: 4±0.5 N m.
1
2
3
4
Rigging Frame Installation Guide
FITTING HIGHLITE IN THE FRAME
Rev B March 2015
Fitting HIGHlite In The Frame
HIGHlite
2D
660
740
HIGHlite
3D
660
HIGHlite
2D
8000
Required parts
Part
Quantity
Rigging frame
1
M6x20 button head screws
6
ø6 spring lock washers
6
ø6.2 insulation sleeves
12
Setup
1. Place the projector upside down on a suitable flat surface and remove
the four adjustable feet 1 .
Notes
This procedure requires two
persons.
1
1
1
1
Rigging Frame Installation Guide
FITTING HIGHLITE IN THE FRAME
Rev B March 2015
Setup (continued)
2. Insert six of the ø6.2 insulation sleeves in the M6 screw holes 2 on the inside of the frame.
Notes
This procedure requires two
persons.
It is important to use the sleeves
as they provide galvanic isolation.
2
2
2
2
2
2
Rigging Frame Installation Guide
FITTING HIGHLITE IN THE FRAME
Rev B March 2015
Setup (continued)
3. Position the rigging frame over the projector so that the adjustment screws 3 are at the back, aligning the M6 screw holes 4 .
Ensure that the projector plate 5 is flat against the body of the projector.
This can be achieved by placing the projector on a surface which is smaller than
the frame, allowing full contact between the plate and the projector.
Notes
This procedure requires two
persons.
3
3
4
4
4
4
4
4
5
Rigging Frame Installation Guide
FITTING HIGHLITE IN THE FRAME
Rev B March 2015
Setup (continued)
4. Place the other six ø6.2 insulation sleeves over each M6 screw hole. Place a ø6 spring lock washer over each ø6.2 insulation sleeve.
Secure the six M6x20 button head screws 6 into each hole. Ensure each screw runs through the sleeves and catches into the
corresponding M6 hole in the projector surface.
Notes
This procedure requires two
persons.
It is important to use the sleeves
as they provide galvanic isolation.
Torque: 4±0.5 N m.
6
6
6
6
6
6
Rigging Frame Installation Guide
FITTING HIGHLITE IN THE FRAME
Rev B March 2015
Order of components in assembly with HIGHlite
1
M6x20 button head screw
2
ø6 spring lock washer
3
ø6.2 insulation sleeve
4
Projector plate
Notes
This procedure requires two
persons.
It is important to use the washers
as they provide galvanic isolation.
Torque: 4±0.5 N m.
1
2
4
3
3
Rigging Frame Installation Guide
ADJUSTMENT OPTIONS
Rev B March 2015
Adjustment Options
Roll
Use the adjusting screws on the left and right to roll the projector by
approximately ±5º. Use the adjusting screw on the left to roll to the left and
the screw on the right to roll to the right.
Pitch
Use the two adjusting screws to adjust the pitch by approximately ±5º. Apply
equal adjustment to both screws.
Yaw
Use the adjustment screw positioned underneath the projector to adjust the
yaw by approximately ±5º.
Notes
±5º
±5º
±5º
±5º
Rigging Frame Installation Guide
STACKING PROJECTORS
Rev B March 2015
Stacking Projectors
1. Position the top projector so that the four stacking holes 1 are exactly above the M8 threaded rods 2 .
2. To secure the installation, tighten by hand using the wing nut 3 until it is very difficult to turn one more time.
3. Tighten the M8 nut 4 with a torque value of 5 N m using a dynamometric wrench.
Notes
This procedure requires two
persons.
Make sure the screw is in a
straight position, perpendicular to
the frame.
Correct
Incorrect
1
2
3
4
Rigging Frame Installation Guide
CEILING INSTALLATION
Rev B March 2015
Ceiling Installation
Ceiling installation using 750 kg / 1650 lb Doughty clamps
Fit the square to round adaptors 1 and secure the clamp to the frame.
Notes
For information on weight
restrictions for installations using
the Doughty clamps, see Maximum
Weight Loads further in this guide.
Parts of the frame are unsuitable for
fitting square to round adaptors. See
Safe fitting areas - bottom and
Safe fitting areas - top for more
information.
1
Rigging Frame Installation Guide
CEILING INSTALLATION
Rev B March 2015
Safe fitting areas - bottom
Square to round adaptors should only be fitted in the areas shown below.
510 mm (20.07 in)
510 mm (20.07 in)
113 mm (4.44 in)
113 mm (4.44 in)
65 mm (2.55 in)
113 mm (4.44 in)
113 mm (4.44 in)
65 mm (2.55 in)
Notes
For information on weight
restrictions for installations using
the Doughty clamps, see Maximum
Weight Loads further in this guide.
Rigging Frame Installation Guide
CEILING INSTALLATION
Rev B March 2015
Safe fitting areas - top
Square to round adaptors should only be fitted in the areas shown below.
Notes
For information on weight
restrictions for installations using
the Doughty clamps, see Maximum
Weight Loads further in this guide.
510 mm (20.07 in)
510 mm (20.07 in)
300 mm (11.81 in)
300 mm (11.81 in)
Rigging Frame Installation Guide
CEILING INSTALLATION
Rev B March 2015
Ceiling installation using the truss mount (optional accessory)
Attach the truss mount to the top frame in the stack by driving
the screws 1 into the mounting holes on the frame 2 .
1
1
1
1
1
2
Notes
For information on weight
restrictions for installations using the
truss mount, see Maximum Weight
Loads further in this guide.
Torque: 4±0.5 N m.
Rigging Frame Installation Guide
CEILING INSTALLATION
Rev B March 2015
Adjusting ceiling installations with the truss mount
Lift the handle 1 to allow 360° rotation adjustment.
The inclination angle can be adjusted by 10% at the upper part (rough adjustment) and by
2% at the lower part (fine adjustment).
Use the four adjustment screws 2 for fine adjustment.
Notes
2
Fine adjustment (up to 2º)
Rough adjustment (up to 10º)
1
360º
Rigging Frame Installation Guide
MAXIMUM WEIGHT LOADS
Rev B March 2015
Maximum Weight Loads
Truss mount installations
The maximum weight load for a truss mount installation is 137.84 kg (302.03 lb).
Use the truss mount with up to two projectors per installation, as shown in the illustration.
Notes
Ensure the load capacity of the
supporting structure is sufficient
to carry the weight of the entire
installation, up to 150 kg (330.69
lb) incl. lenses, cabling, etc.
M-Vision 930
HIGHlite
HIGHlite Laser
Titan
Rigging Frame Installation Guide
MAXIMUM WEIGHT LOADS
Rev B March 2015
Ceiling installation using 750 kg / 1650 lb Doughty clamps
The maximum weight load for a ceiling installation using Doughty clamps is 137.84 kg (302.03 lb).
Use Doughty clamps to mount up to two projectors as shown in the illustration.
Notes
Ensure the load capacity of the
supporting structure is sufficient
to carry the weight of the entire
installation, up to 150 kg (330.69
lb) incl. lenses, cabling, etc.
HIGHlite Laser
HIGHlite
M-Vision 930
Titan
Rigging Frame Installation Guide
MAXIMUM WEIGHT LOADS
Rev B March 2015
Table mounts
The maximum weight load for a table mount installation is 210 kg (462.97 lb).
Mount up to three projectors as shown in the illustration.
Make sure the surface can support the weight of the installation.
Notes
HIGHlite Laser
HIGHlite
M-Vision 930
Titan
Rigging Frame Installation Guide
DIMENSIONS
Rev B March 2015
Dimensions
Rigging frame
Notes
Frame only weight: 20 kg / 44.09 lb
695 mm / 27.36 in
360 mm / 14.17 in
670 mm / 26.37 in
815 mm / 32.08 in
360 mm / 14.17 in
490 mm / 19.29 in
Rigging Frame Installation Guide
DIMENSIONS
Rev B March 2015
Truss mount
Notes
Truss mount weight: 4.5 kg / 8.81 lb
284 mm / 11.18 in
250.2 mm / 9.85 in
164.7 mm / 6.48 in
159 mm / 6.26 in
Rigging Frame Installation Guide
DIMENSIONS
Rev B March 2015
This page is intentionally left blank.
115-918B Rigging Frame Installation Guide
Contact Information:
Digital Projection Limited
Greenside Way, Middleton
Manchester M24 1XX, UK
Registered in England No. 2207264
Registered Office: as above
Tel
(+44) 161 947 3300
Fax
(+44) 161 684 7674
[email protected]
[email protected]
www.digitalprojection.co.uk
Digital Projection Inc.
55 Chastain Road, Suite 115
Kennesaw, GA 30144, USA
Tel
(+1) 770 420 1350
Fax
(+1) 770 420 1360
[email protected]
www.digitalprojection.com
Digital Projection China
中国 北京市 朝阳区 芍药居北里101号
世奥国际中心A座2006室(100029)
Rm A2006
ShaoYaoJu 101 North Lane
Shi Ao International Center
Chaoyang District
Beijing 100029, PR CHINA
Tel
(+86) 10 84888566
Fax
(+86) 10 84888566-805
[email protected]
www.dp-china.com.cn
Digital Projection Asia
16 New Industrial Road
#02-10 Hudson Technocentre
Singapore 536204
Tel
(+65) 6284-1138
Fax
(+65) 6284-1238
www.digitalprojectionasia.com