Fujitsu Eternus DX80 S2 Hardware Installation

Specifications

Brand: Fujitsu
Category: Network Storage Server
Model: Eternus DX80 S2 (Hardware Installation)
File Type: PDF
File Size: —
Pages: 22

Read Online

Read the Fujitsu Eternus DX80 S2 Hardware Installation online using the built-in PDF viewer.

Text of the manual

ETERNUS DX80 S2 and DX90 S2

Hardware Installation Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2

Backend Cabling QSFP

Power On Procedure Power Off Procedures Operator Panel - Function Button Hardware Installation ETERNUS DX80 S2 and DX90 S2 Copyright Fujitsu Technology Solutions, Release August 2011 Content 1

Package Contents (1)

Controller Enclosure Kit Installation poster Documentation CD Rack mount kit Controller Enclosure • Single Controller Module • Dual Controller Module Left and right Flange Cover Push pin tool 2 x power cords Safety Manual Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 2

Package Contents (2)

Drive Enclosure Kit Installation poster Rack mount kit Drive Enclosure 2 x power cords 1 x QSFP (SAS) cable • Single IOM configuration 2 x QSFP (SAS) cables • Dual IOM configuration Safety Manual Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 3

Rack Mounting (1)

For FTS (CEMEA &I) only Rack-mount kit Rack mount installation overview Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 4

screws (10 mm)

2U Bracket Rack Mounting (2) Attach the 2U Bracket to the right rear rack pillar The M5 centering screws should be inserted in the 1st and 6th holes above the base line of the Enclosures Insert the pins of the left hand side slide rail in the 1st and 3rd hole Start counting from the bottom of the 2U Bracket Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 Base line of the Controller Enclosure 5

M5 Cage nut

Rack Mounting (3) Push the M5 cage nut into the 2nd hole of the front rack pillar Above the base line of the Enclosures At the left hand side fix the slide rail to the front pillar with The M5 centering screws The M5 pan head screws Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 M5 Centering screw (10 mm) M5 Pan head screw (10 mm) Base line of the Controller Enclosure 6

Rack Mounting (4)

For the left hand side rail Insert the pins in the holes of the rear pillar Fix the other side of the slide rail to the front pillar • Repeat the same procedure as done before with the left hand side slide rail Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 Base line of the Controller Enclosure M5 Cage nut Base line of the Controller Enclosure M5 Pan head screw (10 mm) M5 Centering screw (10 mm) 7

Rack Mounting (5)

Front view of the rack installation Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 8

Rack Mounting (6)

Fit the Controller Enclosure and/or Drive Enclosure to the rack For better stability, a rack has to be filled by starting from the bottom Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 9

Copyright Fujitsu Technology Solutions, Release August 2011

Hardware Installation ETERNUS DX80 S2 and DX90 S2 For FTS (CEMEA&I) only Connect the rack PDUs (Power Distribution Units) to independent AC power phases Make sure that the AC power switches on each Enclosure are turned off before connecting their power cables Connect each Power Supply of an Enclosure to different Power Distribution Units PSU#0 inlet PSU#1 inlet PSU#0 inlet PSU#1 inlet Left Rack PDU Right Rack PDU Always follow the local power cabling regulations! 10

Backend Cabling QSFP (1)

SAS Port at the CM or IOM6 (SAS Expander) Connect SAS (OUT) ports and SAS (IN) ports by daisy-chain Start in ascending order from the Controller Enclosure Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 Drive Enclosure# 02 Drive Enclosure #01 Controller Enclosure 11

Backend Cabling QSFP (2)

Follow the SAS port labels at the Enclosures This will point to the correct cabling This sign means "IN" and this sign means "OUT" Connect the cables according the labels showing direction ( and ) SAS ports of the Controller Enclosure always have the type "OUT" Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 Connect with the port where is indicated Connect with the port where is indicated DE CE OUT IN Cable symbol OUT 12

Backend Cabling QSFP (3)

QSFP connection between racks To connect QSFP cable between two racks an expansion cable of 3 or 6 meters is used Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 13

Single / Dual Controller Update

A single CM configuration is allowed to be upgraded to a dual CM configuration in the field Also the Drive Enclosure need to be upgraded Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 CE CM #0 DE IOM6 DE IOM6 CE DE IOM6 DE IOM6 IOM6 IOM6 Single CM Dual CM CA CA CM#0 CA CA CM#1 CA CA 1 CM to 2 CM upgrade parts CA: Channel Adapter IOM: IO module DE: Device Enclosure 14

Power On Procedure (1)

The ETERNUS DX S2 systems can be Powered On directly from the Controller Enclosure Push the Power Switch • The "Power" LED of the CE switches on • The power on sequence takes about 2 minutes • If everything is OK, the green Ready LED in the CE and the green Power LED in the DE switch on Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 Power O Fault O Active O Power O Ready O Fault O Maint/ID O Cache O 15

Power On Procedure (2)

Controller Enclosure LEDs Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 POWER LED Constant green when the power is turned on READY LED Constant green when device is available for use FAULT LED Constant amber when a failure is detected in the ETERNUS DX system Blinks in amber when a component which requires preventive maintenance is detected MAINT/ID LED Constant green when the system has its status set to Maintenance Blinks green Status of all components needs to be verified with the GUI or CLI Locate functionality enabled by the GUI or CLI CACHE LED Constant green when data exists in cache memory Blinks in green when cached data is saved to the flash memory 16

Power On Procedure (3)

Drive Enclosure LEDs Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 LINE LED AC power is supplied to the Drive Enclosure FAULT LED Constant amber when a failure is detected in the Drive Enclosure POWER LED The Drive Enclosure is operating normally DE-ID (7-segment) Shows a 2-digit Drive Enclosure ID Is assigned automatically by the SAS backend cabling 2.5" Drive Ecnlosure 3.5" Drive Ecnlosure 17

Power Off Procedure

Verify with the customer that all server I/O is stopped Also confirm that the "CACHE" LED in the Operator Panel is off Hold down the "Power Switch" of the Controller Enclosure for approximately 5 seconds The ETERNUS DX system will shutdown all Enclosures gracefully In case of moving ETERNUS to a new location, you naturally have to also disconnect the AC power cords from the PDUs after the system is powered off Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 Make sure the CACHE LED of the Controller Enclosure is off 18

Operator Panel - Function Button (1)

Remove the plastic Flange Cover to get access to the Function Button The Function Button is located next to the Power Switch Use the pin tool to operate Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 Function Button Power Button 2.5" Controller Enclosure 3.5" Controller Enclosure 19

Operator Panel - Function Button(2)

The operation can be performed by carrying out the following steps To toggle the system status between "Maintenance" and "Normal" • Keep the Function Button pushed for three seconds • The MAINT/ID LED lights green when the system is in Maintenance mode • The MAINT/ID LED is off when the system is in Normal mode Switch the functionality of Master CM to the other Controller Module • Push down the Function Button twice within three seconds • The Master LED lights green to indicate the Master CM Reset the LAN ports of the CM to the default values • Push down the Function Button three times within three seconds • The MAINT/ID LED blinks green for a few seconds Copyright Fujitsu Technology Solutions, Release August 2011 Hardware Installation ETERNUS DX80 S2 and DX90 S2 20

Other Network Storage Server Manuals