Field Controls CK-20FV Quick Start Manual

Text of Field Controls CK-20FV Quick Start Manual

Please retain these instructions after installation.

This device MUST be installed by a qualifi ed agency in accordance with the manufacturer's installation instructions. The defi nition of a qualifi ed agency is: any individual, fi rm, corporation or company which either in person or through a representative is engaged in, and is responsible for, the installation and operation of HVAC appliances, who is experienced in such work

page 2 of 8

MOUNTING JUNCTION BOX The junction box can be mounted at the venter or remotely mounted away from the venter. (See Figures 1 & 2) 1. Remove one of the knockouts from the side of the junction box. Install the fl exible conduit connector onto the CK-20FV junction box and secure with fastening nut. If remote mounting the CK-20FV junction box, mount the fl exible conduit connector onto a 2" x 4" installer supplied junction box. 2. Fasten the fl

page 3 of 8

INSTALLATION OF GAS PRESSURE SWITCH CAUTION: Check gas control valve pressure. Pressure must not exceed 14” WC pressure. 1. Remove pressure tap plug in gas valve. (See Figure 3) NOTE: If installing on an existing appliance, shut off gas supply to gas valve before plug removal. 2. Replace the pressure tap plug with the 1⁄8” pipe nipple and pipe tee. Install pressure tap plug at the bottom of the pipe tee. (See Figure 4) 3. Install the gas

page 4 of 8

DRAFT HOOD SAFETY SWITCH INSTALLATION NOTE: 12 ga. wire must be used when wiring safety spillage switches, to reduce the voltage drop in the thermocouple circuit. 1. Remove the thermocouple from the gas control valve. (See Figure 3) 2. Thread the junction block into the thermocouple port and thermocouple into the bottom of the junction block. Connect lead wire from the junction block to the jacketed lead wires or wire enclosed in an accepted wi

page 5 of 8

Diagram A WIRING CAUTION: Disconnect electrical power when wiring power venter. Wire the venter motor and controls in accordance with the National Electrical Code, manufacturer’s recommendations and/or applicable local codes. Units must be grounded. Check ground circuit to make certain that the unit has been properly grounded. The wiring should be protected by an overcurrent circuit device rated at 15 amperes. CAUTION must be taken to ensure

page 6 of 8

P/N 46285000 Rev K 01/18 Diagram B WIRING 750mV GAS VALVE SYSTEM WITH ELECTRONIC TEMPERATURE CONTROL CAUTION: Disconnect electrical power when wiring power venter. When wiring with a power-pile system having an intergrated electronic control, which have a diagnostic LED indicator; please refer to Diagram B. You will not use the TCA thermocouple adapter, supplied with the CK-20FV. Install the GSK spill switches per instruction and connect to t

page 7 of 8

TROUBLE SHOOTING HINTS 1. Venter does not activate when thermostat calls for heat: a. Check wiring. b. Check gas pressure switch for continuity across terminals when gas valve is pressurized. c. Check gas pressure. 2. Flue gas odor: a. Check system draft. b. Check for negative pressure in building. 3. Pilot will not stay lit on water heater: a. Solder all spillage switch wire terminal connections. b. Check reset buttons on spillage switches. c.

Phone: 252.522.3031 • Fax: 252.522.0214

www.fieldcontrols.com © Field Controls, LLC P/N 46285000 Rev K 01/18 This manual may be downloaded and printed from the Field Controls website (www.fi eldcontrols.com) WARRANTY For warranty information about this or any Field Controls product, visit: www.fi eldcontrols.com Field Controls Technical Support 1.800.742.8368 fi eldtec@fi eldcontrols.com

Field Controls Control Unit Owners Instructions: