1. Package Inside
In parallel kit, you will find the following items in the package:
1 PCS of parallel board
1 PCS of parallel cable
3 PCS OP relay board
1 PCS of share current cable
3 PCS of 2-pin red/black cables、3 PCS of 4-pin brown cables and 1 PCS of14-pin grey cable
3 PCS of brown wires(each with a yellow& white core) and 1 PC
2.2 Replace the CNTL board and COMMUNICATION board
Please ignore this step, if the the units you have bought were suitable for parallel function already.
For Gallon 3-3 UPS (10K,15K,20K,30K),there are 2 control boards, one for PFC control , and the other
for INV control, the following picture showing the different between these two boards, the pa
Step 1: Replace PFC control board:
Remove the white glue.
Disconnect the 3-pin cable from CN7
of the PFC control board, demount
the small PCBA board.
Demount the 3 white screws,
disconnect the 50-pin cable.
Replace the PFC control board with a
new one. It is better assemble the
small PCBA first, then assemble the
new PFC control board by install the
3 screws
Step 2: Replace the INV control
board:
Remove the white glue, demount
the screw. Then pull the INV control
board.
Flipping over the INV control board,
you can see the glue on the
connectors, remove the glue, then
dis connect all the cables.
Replace the INV control board
with an new one, assemble the
new board back to the INV1&2
board.
Step 3: Replace the communication
board:
Take a new communication board,
demount the 2 screws of the DB-15
port.
Disconnect
the
cables
on
the
communication board, and demount
the srews that used to fasten the
communication board to the rear
panel.
Replace the board with a new one,
connect the cables, install the
screws.
2.3 Parallel kit installation
Step 1:
Step 3: Assemble the OP relay
boards to the location left of the
OP EMI board.
Step 4: Connect the OP relay
control and OP voltage detect
cables (4-pin brown cable):
Connect CN001 to CN15 of
INV1&2 board.
Connect CN002 to CN16 of
INV1&2 board.
Connect CN003 to CN15 of INV3
board.
Step 5: Connect the wires that
demounted from the OP EMI
board by “step2”:
Step 7: Take a new parallel
board, demount the 4 screws
from the parallel port ( DB15
Connectors)
Connect the “Parallel board power
supply cable” to CN9 of parallel
board.
Connect the “S phase current
equalizer cable” to CN10 of
parallel board.
Connect the “T phase current
equalizer cable” to CN11 of
parallel board.
Step 8: Remove covers for
para
Step 10: Connect the “Parallel
board power supply cable” (Short
red/black cable) to CN10 of
communication board.
Step 11: Connect the “S phase
current equalizer cable” (the
longer red/black cable) to “CN20”
of INV 1&2 board.
Step 12: Connect the “T phase
current
equalizer
cable”
the
longest red/black cable) to “CN 6”
of INV 3 board.
Step 13: Connect the 14-pin
grey cable to CN11 of INV control
board:
Please reference to Step2 of
part 2.2 to demount the INV
control board from the INV1&2
board.
Connect the 14-pin grey cable
to CN11 of INV control board.
Step 14: Assemble the INV
control board back to INV1&2
board, and then make the 14-PIN
grey cable through the middle
iron board.
Step 15:
Above is suitable for GALLON 3-3 10k, 15k, 20K,30K standard modle, for long backup modle, the difference is the
OP relay boards assembling, the following picture is for reference when assembling OP relay boards to the long
backup unit:
The Location Of OP Relay Board For Long Backup Unit
3. Wiring Connection for Parallel Operation
Please follow the b