Wicksteed Activitynet14 Installation Instructions Manual
Text of Wicksteed Activitynet14 Installation Instructions Manual
Space requirements Page 2
Free height of fall Page 2
Installation Instructions Page 2
Foundation Requirements Page 3
Foundation Setting Page 4
Excavation & Positioning Page 5
Assembly Instructions Page 6
Maintenance & Contact Page 7
Details
4m Activitynet14
Installation Instructions
Using Rubber Safety Surface
Product Overview
The Activitynet14 Activity Net has been designed to be used by children from 3
year
Space requirements & Safety Clearances
Installation instructions
The Activitynet14 Activity Net is delivered in three sections.
Section One is the polished stainless stell mast which is to be mounted over the
central spigot of the foundation steelwork leaving the top of the mast to accept
the aluminium dome. This is attached to the top of the net.
Section Two is the net, complete with aluminium dome to be inserted into the top
Top of Rubber Safety Surface
Top Surface of Concrete
Product Activitynet14
Foundation requirements
General
This net has been designed to allow a rubber safety surface to be used in conjunction
with corner boxes. The surface thickness should be based on the CFH of 850mm. The
boxes are supplied with a tile glued to the lid, this ensures the finished ground
level is the required 400mm above the concrete.
It is recomended the area is prepa
All dimensions to the
centre of the hole in
the anchor
50
800
355
Safety anchor positioned
in hole at back of box
The eye of the
anchor is directly
over the front of the
concrete block
Safety Anchor
Product Activiynet14
Corner Foundation Hole: 1000x1000x800 Centre Foundation Hole: 800x800x800
Page 4
Datum Peg to
Top Hole Corner
Anchor
Shuttering, pegged and nailed
timber frame to support anchor
and corner box during concreting
Product Activitynet14
Excavation &
Foundation
Positioning
Procedure
In loose ground, it may
be necessary to use
timber framework (or
shuttering) to prevent
soil falling into the
hole. It will also
prevent an unnecessary
excess volume of
concrete being used.
Concrete to be in 30/N
mm2 mix. Total volume
required: 3.712 cubic
met
1) To lift the net and mast into their final position, connect a sling (rope or
webbing) to the upper part of the mast and lift using the excavating machine.
Note: do not, under any circumstances, allow the lifting of the item using only the
net as support as this can cause irreparable damage to the net. The mast must take the
support. The certified excavator operator will be able to assist in this operation.
2) locate the base of the mast over
Maintenance & Inspection
General
The structure should be inspected and maintained in accordance with the
recommendations as detailed in EN-1176-Part-7: Guidance on installation, inspection,
maintenance and operation for playground equipment.
If any part of the equipment is found to be unsafe during an inspection, and that
part cannot be repaired or replaced immediately, the equipment unit or part(s)
concerned should be secured against use. This may involve