Emerson Rosemount 2160 Quick Start Manual
Text of the manual
Quick Start Guide
00825-0100-4160, Rev CC
February 2021
Rosemount
™ 2160 Wireless Level
Detector
Vibrating Fork
About this guide...........................................................................................................................3
Installation................................................................................................................................... 6
Configuration...................................................
About this guide
This Quick Start Guide provides basic guidelines for the Rosemount 2160.
Refer to the Rosemount 2160 Reference Manual for more instructions. The
manual and this guide are also available electronically at Emerson.com/
Rosemount.
1.1
Safety messages
NOTICE
Power module considerations.
Each Power Module contains two "C" size primary lithium/t
Shipping considerations for wireless products.
The unit was shipped to you without the power module installed. Remove
the power module prior to shipping.
Each power module contains two “C” size primary lithium batteries. Primary
lithium batteries are regulated in transportation by the U. S. Department of
Transportation, and are also covered by IAT
Process leaks could result in death or serious injury.
Ensure the level detector is handled carefully. If the process seal is damaged,
gas might escape from the vessel (tank) or pipe.
WARNING
Physical access
Unauthorized personnel may potentially cause significant damage to and/or
misconfiguration of end users’ equipment. This could be intentional
Fork alignment in a pipe installation
The fork is correctly aligned by positioning the groove or notch as indicated
(Figure 2-1).
Figure 2-1: Correct Fork Alignment for Pipe Installation
OK
A
B
OK
A
B
A. Tri Clamp process connections have a circular notch
B. Threaded process connections have a groove
2.2
Fork alignment in a vessel (tank) i
Mounting the threaded version
2.3.1
Threaded vessel (tank) or pipework connection
Procedure
1. Seal and protect the threads. Use anti-seize paste or PTFE tape
according to site procedures.
A gasket may be used as a sealant for BSPP (G) threaded connections.
2. Screw the level detector into the process connection.
Note
Tighten using the hexagon nut only.
Threaded flange connection
Procedure
1. Place the customer-supplied flange and gasket on the vessel (tank)
nozzle.
A
A. Gasket (customer supplied)
2. Tighten the bolts and nuts with sufficient torque for the flange and
gasket.
3. Seal and protect the threads. Use anti-seize paste or PTFE tape
according to site procedures.
A gasket may be used as a seal